4019 N DENNY AVE 91604
Certificate Information: 4019 N DENNY AVE 91604
- Application / Permit
- 21010-10000-00819
- Plan Check / Job No.
- B21LA02949
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)&(d). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2021 | LAMAR DAVIS |
| Corrections Issued | 3/2/2021 | LAMAR DAVIS |
| Quality Review Completed | 3/10/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 9/15/2021 | LAMAR DAVIS |
| Plan Check Approved | 1/21/2022 | LAMAR DAVIS |
| Issued | 1/25/2022 | APPLICANT |
| CofO in Progress | 12/7/2022 | JACK KARGODORIAN |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
| CofO Issued | 3/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 6/15/2021 | EDDI ZEPEDA |
| Address approval | Cleared | 6/18/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 6/18/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 8/21/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/25/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 8/31/2021 | KURT CORRAL |
| Miscellaneous | Cleared | 1/21/2022 | LAMAR DAVIS |
| ZI | Cleared | 1/21/2022 | NELSON RODRIGUEZ |
Contact Information
| Architect | Smith,, Justin Keith; Lic. No.: C37880 | 7037 DUSTY LANE MODESTO, CA 95357 |
| Contractor | Owner-Builder | , |
| Engineer | Gregorio,, Andrew Mario; Lic. No.: S6343 | 5380 BERKELEY RD HUGHSON, CA 95326 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/31/2022 | Approved | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Partial Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 3/21/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 3/21/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/29/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 3/29/2022 | Approved | THOMAS FINNILA |
| HVAC-Rough | 3/29/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/29/2022 | Partial Approval | THOMAS FINNILA |
| Insulation | 4/5/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/18/2022 | Approved | THOMAS FINNILA |
| Service/Power Release | 5/18/2022 | Not Ready for Inspection | DAVID MATSON |
| Footing/Foundation/Slab | 5/19/2022 | Approved | THOMAS FINNILA |
| Green Building Final | 5/19/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 5/24/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Final | 5/24/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 5/24/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/24/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/23/2022 | Corrections Issued | ROBERT GOLD |
| Final | 7/14/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 7/14/2022 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Final | 7/14/2022 | Approved | THOMAS FINNILA |
| Service/Power Release | 7/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 12/6/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 12/6/2022 | Approved | JACK KARGODORIAN |
| Service/Power Release | 12/6/2022 | Approved | JACK KARGODORIAN |