4134 W MONROE ST 90029

Certificate Information: 4134 W MONROE ST 90029

Application / Permit
21010-10000-00814
Plan Check / Job No.
B21LA02929
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1 STORY ADU ON EXISTING MULTIFAMILY PROPERTY PER ENGINEER DESIGN ADM-2021-2737-ADU. (TWO ADUs PER STATE LAW, CA Govt. 65852.2(e)(1)(D), LAMC 12.22A.33(c)(d), (g))
Permit Issued
Issued on 8/8/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 AUNG SOE
Corrections Issued 3/16/2021 AUNG SOE
Quality Review Completed 3/18/2021 EUGENE BARBEAU
Applicant returned to address corrections 8/5/2021 AUNG SOE
Building Plans Picked Up 8/6/2021 APPLICANT
Plan Check Approved 7/6/2022 AUNG SOE
Issued 8/8/2022 APPLICANT
CofO in Progress 6/28/2023 FREDDIE RIVERA
Permit Finaled 7/1/2023 DEROLD HAUFF
Permit Finaled 7/1/2023 DEROLD HAUFF
CofO Issued 7/1/2023 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 3/25/2021 DANALYNN DOMINGUEZ
Tenant Habitability Plan Cleared 4/26/2021 RICHARD BRINSON
Address approval Cleared 4/28/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/29/2021 RENZ SORIANO
Sewer availability Cleared 4/29/2021 RENZ SORIANO
Grading Pre-Inspection Cleared 6/21/2021 PATRICK MISCHLICH
Hydrant and Access approval Cleared 9/13/2021 ROBERT DUFF
Low Impact Development Cleared 6/8/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/10/2022 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Jason K; Lic. No.: S6095 1529 W LONGHILL DR      MONTEREY PARK, CA 91754

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2022 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 9/19/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 9/19/2022 Partial Approval FREDDIE RIVERA
Underground Mechanical 9/19/2022 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 10/19/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 10/19/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval FREDDIE RIVERA
Wood Frame 12/1/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 12/19/2022 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 12/21/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 1/10/2023 Partial Inspection FREDDIE RIVERA
Underground Mechanical 1/10/2023 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 1/13/2023 Not Ready for Inspection FREDDIE RIVERA
Underground Mechanical 1/13/2023 Partial Approval FREDDIE RIVERA
Underground Mechanical 1/17/2023 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 1/18/2023 Approved FREDDIE RIVERA
HVAC-Rough 1/19/2023 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 1/23/2023 Partial Inspection FREDDIE RIVERA
Green Building Rough 1/23/2023 Partial Inspection FREDDIE RIVERA
HVAC-Rough 1/23/2023 Approved FREDDIE RIVERA
Sewer 1/23/2023 Partial Approval FREDDIE RIVERA
Verify Sprinkler Sign Off 1/23/2023 Approved FREDDIE RIVERA
Underground Mechanical 1/27/2023 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 2/2/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Corrections Issued FREDDIE RIVERA
Green Building Rough 2/2/2023 Approved FREDDIE RIVERA
Insulation 2/9/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 2/9/2023 Partial Approval FREDDIE RIVERA
Drywall Nailing 2/16/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/14/2023 Partial Inspection FREDDIE RIVERA
Shower Pan 3/14/2023 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 3/16/2023 Approved FREDDIE RIVERA
Shower Pan 3/16/2023 Corrections Issued FREDDIE RIVERA
Shower Pan 3/22/2023 Approved FREDDIE RIVERA
ELECTRICAL-Final 4/3/2023 Approved FREDDIE RIVERA
HVAC-Final 4/3/2023 Partial Inspection FREDDIE RIVERA
Green Building Final 4/12/2023 Partial Inspection FREDDIE RIVERA
HVAC-Final 4/12/2023 Approved FREDDIE RIVERA
PLUMBING-Final 4/12/2023 Partial Inspection FREDDIE RIVERA
Final 4/13/2023 Corrections Issued STUART CHAPMAN
PLUMBING-Final 4/13/2023 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Approved STUART CHAPMAN
Final 4/14/2023 Corrections Issued FREDDIE RIVERA
Gas Test 4/14/2023 Partial Inspection FREDDIE RIVERA
Service/Power Release 4/14/2023 Partial Inspection FREDDIE RIVERA
Smoke Detectors 4/14/2023 Approved FREDDIE RIVERA
Final 4/21/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 4/21/2023 Approved FREDDIE RIVERA
PLUMBING-Final 4/21/2023 Approved FREDDIE RIVERA
Service/Power Release 4/21/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 4/25/2023 Approved FREDDIE RIVERA
Final 4/28/2023 Partial Inspection FREDDIE RIVERA
Gas Test 4/28/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 4/28/2023 Partial Inspection FREDDIE RIVERA
Service/Power Release 5/8/2023 Corrections Issued FREDDIE RIVERA
Final 6/9/2023 Corrections Issued FREDDIE RIVERA
Service/Power Release 6/9/2023 Partial Inspection FREDDIE RIVERA
Final 6/21/2023 Conditional Approval FREDDIE RIVERA
Service/Power Release 6/21/2023 Approved FREDDIE RIVERA