12600 W MITCHELL AVE 1-2 90066

Certificate Information: 12600 W MITCHELL AVE 1-2 90066

Application / Permit
21010-10000-00791
Plan Check / Job No.
B21LA02855
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 4-story, Type VA Single Family Dwelling with attached 2-car garage at ground floor over Type IA ADU basement and rooftop deck per Small Lot Subdivision pursuant to Tentative Tract Map No.VTT-82766-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded. Lot 1.
Permit Issued
Issued on 8/4/2022
Issuing Office
Current Status
CofO Issued on 12/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 8/4/2022 RODOLFO ARIAS
Issued 8/4/2022 APPLICANT
CofO in Progress 12/5/2025 WILBER ROSALES
Permit Finaled 12/8/2025 RICHARD STEINBACH
CofO Issued 12/8/2025 RICHARD STEINBACH
Permit Finaled 12/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Work Adjacent to Public Way Cleared 12/3/2021 SAUL GARCIA
Address approval Cleared 1/25/2022 HISASHI KOBAYAKAWA
Building over 36-ft Cleared 1/26/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/26/2022 CALOSHA APPROVED
Hydrant and Access approval Cleared 2/1/2022 JOHN CONNEALLY
Construction near power lines Cleared 3/3/2022 RIDWAN HARDY
Highway dedication Cleared 4/20/2022 RAYMOND MUGAMBWA
Miscellaneous Cleared 4/20/2022 RAYMOND MUGAMBWA
Permit Cleared 4/20/2022 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 4/25/2022 NIKTA MOUSAVI
Low Impact Development Cleared 5/10/2022 AMMAR ELTAWIL
Frnt yard landscape/Water mgmt Cleared 5/12/2022 JASON CHAN
Miscellaneous Cleared 5/12/2022 JASON CHAN
Tract Map conditions Cleared 5/12/2022 JASON CHAN
ZA Case Cleared 5/12/2022 JASON CHAN
Roof/Waste drainage to street Cleared 5/19/2022 NIKTA MOUSAVI
Trees in Parkway Cleared 5/19/2022 ADALBERTO VERA
Green Code Cleared 5/20/2022 RODOLFO ARIAS
Sewer availability Cleared 5/20/2022 NIKTA MOUSAVI
Specific Plan Cleared 6/23/2022 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Alrayes,, Nidham Aram; Lic. No.: C65487 10346 SAMOA AVE      TUJUNGA, CA 91042
Engineer Fawaz,, Abbas Mohamad; Lic. No.: C64765 6756 CORAL LEAF LANE      RIVERSIDE, CA 92506
Landscape Architect Savage,, Michael Sanford; Lic. No.: LA4397 1125 SHEPPARD DRIVE      FULLERTON, CA 92831

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/10/2022 Corrections Issued DAVID FEILER
Special/Order Compliance 8/10/2022 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 8/15/2022 Not Ready for Inspection BOBBY KEY
Underground Mechanical 8/15/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 8/17/2022 Partial Inspection DAVID FEILER
Footing/Foundation/Slab 9/26/2022 Partial Approval DAVID FEILER
Pre-Inspection 9/26/2022 Partial Approval JESUS RODRIGUEZ
Deputy Shotcrete 10/7/2022 Partial Approval JESUS RODRIGUEZ
Deputy Shotcrete 10/18/2022 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 11/1/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/15/2022 Conditional Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 1/18/2023 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 1/18/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 1/18/2023 Corrections Issued JESUS RODRIGUEZ
Deputy Reinf. Concrete 3/23/2023 Conditional Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 4/6/2023 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 4/13/2023 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Partial Approval JESUS RODRIGUEZ
Drywall Nailing 4/24/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval JESUS RODRIGUEZ
Drywall Nailing 5/30/2023 Partial Approval JESUS RODRIGUEZ
Green Building Rough 5/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Approval JESUS RODRIGUEZ
Drywall Nailing 7/19/2023 Partial Approval JESUS RODRIGUEZ
Green Building Rough 7/19/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval EVAN COOPER
Drywall Nailing 8/30/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 8/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
Deputy Wood Construction 9/12/2023 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 12/29/2023 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 1/3/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 1/5/2024 Partial Approval JESUS RODRIGUEZ
HVAC-Final 2/7/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 2/7/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 2/14/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/2/2024 No Access for Inspection JESUS RODRIGUEZ
Green Building Rough 4/2/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/2/2024 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 4/2/2024 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/10/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 4/10/2024 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 4/10/2024 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/18/2024 Corrections Issued JESUS RODRIGUEZ
Verify Sprinkler Sign Off 4/18/2024 Not Ready for Inspection JESUS RODRIGUEZ
Insulation 4/22/2024 Corrections Issued JESUS RODRIGUEZ
Insulation 5/8/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 5/8/2024 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 5/8/2024 Corrections Issued JESUS RODRIGUEZ
Drywall Nailing 6/4/2024 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/1/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 8/1/2024 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 8/1/2024 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 9/12/2024 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 10/23/2024 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 10/23/2024 Partial Approval JESUS RODRIGUEZ
Verify Sprinkler Sign Off 10/23/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 2/26/2025 Partial Approval JESUS PINEDA
Shower Pan 6/3/2025 Approved BOBBY KEY
Shower Pan 6/9/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/9/2025 Partial Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 7/10/2025 Partial Approval JAYLIN GRAVITTE
Drywall Nailing 8/13/2025 Approved WILBER ROSALES
ELECTRICAL-Final 11/19/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 11/19/2025 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 11/19/2025 SGSOV Not Ready WILBER ROSALES
Special/Order Compliance 11/19/2025 No Access for Inspection DAVID FEILER
BUILDING-Rough-Frame 11/21/2025 Approved WILBER ROSALES
ELECTRICAL-Final 11/21/2025 Approved WILBER ROSALES
Final 11/21/2025 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 11/21/2025 Approved WILBER ROSALES
Green Building Final 11/21/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Final 11/21/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 11/21/2025 Approved WILBER ROSALES
Reinforced Concrete Frame 11/21/2025 Approved WILBER ROSALES
Reinforced Masonry Frame 11/21/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved WILBER ROSALES
Service/Power Release 11/21/2025 Not Ready for Inspection WILBER ROSALES
Smoke Detectors 11/21/2025 Approved WILBER ROSALES
Structural Steel Frame 11/21/2025 Approved WILBER ROSALES
Final 12/1/2025 Not Ready for Inspection JESUS PINEDA
Green Building Final 12/1/2025 Approved JESUS PINEDA
HVAC-Final 12/1/2025 Approved JESUS PINEDA
Final 12/3/2025 Corrections Issued WILBER ROSALES
Service/Power Release 12/3/2025 Not Ready for Inspection WILBER ROSALES
Final 12/5/2025 OK to Issue CofO WILBER ROSALES
Service/Power Release 12/5/2025 Approved WILBER ROSALES