1878 W EFFIE ST 90026
Certificate Information: 1878 W EFFIE ST 90026
- Application / Permit
- 21010-10000-00759
- Plan Check / Job No.
- B21LA02759
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1,145SF ACCESSORY DWELLING UNIT AT REAR PER 12.22.A.33. BUILDING SHALL BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THRU-OUT. (2 OF 2)
- Permit Issued
- Issued on 7/31/2021
- Issuing Office
- Current Status
- CofO Issued on 6/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | JOHNNY WU |
| Corrections Issued | 2/24/2021 | JOHNNY WU |
| Quality Review Completed | 3/1/2021 | FARUK SEZER |
| Applicant returned to address corrections | 4/13/2021 | JOHNNY WU |
| Applicant returned to address corrections | 7/23/2021 | JOHNNY WU |
| Plan Check Approved | 7/28/2021 | JOHNNY WU |
| Plan Check Approved | 7/30/2021 | JOHNNY WU |
| Issued | 7/31/2021 | APPLICANT |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| CofO in Progress | 6/13/2022 | THOMAS LOGRASSO |
| CofO Issued | 6/22/2022 | DEROLD HAUFF |
| Permit Finaled | 6/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 2/24/2021 | JOHNNY WU |
| Address approval | Cleared | 3/8/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2021 | WALLIE JONG |
| Permit | Cleared | 3/9/2021 | WALLIE JONG |
| Sewer availability | Cleared | 3/9/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 3/12/2021 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 4/13/2021 | JOHNNY WU |
| Hydrant and Access approval | Cleared | 4/24/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/16/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/15/2021 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Latifian,, Amirmasoud; Lic. No.: C87552 | 13075 PACIFIC PROMENADE 317 PLAYA VISTA, CA 90094 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/27/2021 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 10/27/2021 | Partial Approval | RUBEN SALAS |
| PLUMBING-Rough | 11/3/2021 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/17/2021 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 11/17/2021 | Partial Inspection | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Approved | RUBEN SALAS |
| Deputy Wood Construction | 12/29/2021 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 2/1/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/8/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 2/8/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/8/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/9/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/9/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 2/9/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/9/2022 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 2/9/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/25/2022 | Approved | DANIEL GONZALEZ |
| Insulation | 2/25/2022 | Approved | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 2/25/2022 | Partial Approval | DANIEL GONZALEZ |
| Drywall Nailing | 3/3/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 3/3/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/11/2022 | Approved | THOMAS LOGRASSO |
| Gas Test | 5/10/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 5/10/2022 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Final | 5/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 5/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| Service/Power Release | 5/12/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 5/20/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 5/20/2022 | Approved | THOMAS LOGRASSO |
| Final | 5/26/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/26/2022 | Approved | THOMAS LOGRASSO |
| Green Building Final | 5/26/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 5/26/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 5/26/2022 | Approved | THOMAS LOGRASSO |
| Final | 6/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 6/13/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 6/13/2022 | Approved | THOMAS LOGRASSO |