13101 1/2 W CARL ST 91331
Certificate Information: 13101 1/2 W CARL ST 91331
- Application / Permit
- 21010-10000-00753
- Plan Check / Job No.
- B21LA02745
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ACCESSORY DWELLING UNIT PER WFPP AND GCS 65852.2 & 65852.22
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 3/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2021 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 3/24/2021 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 5/24/2021 | TEODORO DIAZ RODRIGUEZ |
| Issued | 5/24/2021 | APPLICANT |
| CofO in Progress | 10/19/2021 | MICHEL ABAJAN |
| No Progress | 12/11/2021 | MICHAEL TEMPLE |
| CofO in Progress | 3/16/2022 | RONALD MYRICK |
| Permit Finaled | 3/16/2022 | RONALD MYRICK |
| CofO Issued | 3/16/2022 | RONALD MYRICK |
| Permit Finaled | 3/16/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/18/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 4/23/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/23/2021 | MARTIN FRAGOSO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/28/2021 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 5/28/2021 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 5/28/2021 | Approved | MICHEL ABAJAN |
| Sewer | 6/3/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/22/2021 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Partial Inspection | MICHEL ABAJAN |
| Green Building Rough | 6/22/2021 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 6/22/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/22/2021 | Partial Approval | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 6/22/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 7/13/2021 | Partial Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/16/2021 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 7/19/2021 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/19/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/19/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/19/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/19/2021 | Approved | MICHEL ABAJAN |
| Insulation | 7/20/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Insulation | 7/22/2021 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 7/27/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/8/2021 | Approved | JENNIFER RABUCHIN |
| Final | 9/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 9/8/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/8/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 9/8/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 9/8/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/13/2021 | Approved | MICHEL ABAJAN |
| Final | 9/13/2021 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 9/13/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/13/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2021 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 9/13/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 10/7/2021 | Partial Inspection | MICHEL ABAJAN |
| Service/Power Release | 10/7/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 10/19/2021 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 10/19/2021 | Approved | MICHEL ABAJAN |