6708 N RIVERTON AVE 91606
Certificate Information: 6708 N RIVERTON AVE 91606
- Application / Permit
- 21010-10000-00747
- Plan Check / Job No.
- B21LA02729
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 2/5/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | CARLOS MONTES |
| Corrections Issued | 3/5/2021 | CARLOS MONTES |
| Quality Review Completed | 3/10/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/7/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 7/12/2022 | CARLOS MONTES |
| Plan Check Approved | 2/5/2024 | CARLOS MONTES |
| Issued | 2/5/2024 | APPLICANT |
| CofO in Progress | 6/6/2025 | JOSE AVILA |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2021 | CARLOS AGUILERA |
| Highway dedication | Cleared | 7/8/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/25/2022 | KURT CORRAL |
| Frnt yard landscape/Water mgmt | Cleared | 5/27/2022 | LAUREN PADICK |
| Low Impact Development | Cleared | 6/30/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/2/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Coast Builders Group Inc; Lic. No.: 872035-B | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2024 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 4/26/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/9/2024 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Rough | 5/9/2024 | Partial Approval | ROBERT GOLD |
| Insulation | 5/13/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/13/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 6/14/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 8/16/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 8/29/2024 | Not Ready for Inspection | JOSE AVILA |
| Verify Sprinkler Sign Off | 8/29/2024 | Partial Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 9/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/9/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 9/9/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/9/2024 | Approved | JOSE AVILA |
| Sewer | 9/9/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 10/31/2024 | Partial Approval | JOSE AVILA |
| Green Building Rough | 10/31/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/31/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 10/31/2024 | Approved | JOSE AVILA |
| Insulation | 11/4/2024 | Approved | JOSE AVILA |
| Special/Order Compliance | 11/4/2024 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 11/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 11/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/19/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 2/5/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/10/2025 | Corrections Issued | JOSE AVILA |
| Gas Test | 2/10/2025 | Approved | JOSE AVILA |
| HVAC-Final | 2/10/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 2/24/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 2/24/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/28/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/28/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 2/28/2025 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 2/28/2025 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 2/28/2025 | Approved | JOSE AVILA |
| Final | 6/6/2025 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 6/6/2025 | Approved | JOSE AVILA |
| Service/Power Release | 6/6/2025 | Approved | JOSE AVILA |