Excavation/Setback/Form/Re-Bar
|
3/15/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
3/16/2024
|
Partial Approval
|
NICK DANERI
|
|
Deputy Other (see comments)
|
3/18/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/18/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
3/18/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
3/18/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
3/20/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
3/21/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
3/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/26/2024
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Excavation/Setback/Form/Re-Bar
|
3/28/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
3/29/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
3/29/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
3/29/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
4/10/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
4/12/2024
|
Off-Hour Fees Due
|
|
|
Pre-Inspection
|
5/24/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
5/30/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
5/31/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
6/4/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
6/4/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
7/9/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/9/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/10/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/16/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/30/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
8/19/2024
|
Partial Inspection
|
JACOB MYERS
|
|
Deputy Wood Construction
|
8/20/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/20/2024
|
Partial Approval
|
JACOB MYERS
|
|
Special/Order Compliance
|
8/21/2024
|
Corrections Issued
|
JACOB MYERS
|
|
Excavation/Setback/Form/Re-Bar
|
8/22/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
9/5/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/5/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
9/18/2024
|
Conditional Approval
|
ALFREDO LOPEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/18/2024
|
Partial Approval
|
ALFREDO LOPEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/26/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/3/2024
|
Corrections Issued
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/4/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/21/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Insulation
|
12/3/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
12/4/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/9/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/13/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/16/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/24/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Wood Frame
|
12/27/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Insulation
|
1/2/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
1/3/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
1/22/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
2/3/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
3/19/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/21/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/2/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
4/2/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
4/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/9/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
4/22/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
4/24/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
4/28/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
5/13/2025
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Insulation
|
5/19/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
5/29/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Insulation
|
6/5/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
6/9/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
6/12/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
6/23/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
6/25/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
7/3/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
7/8/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
7/11/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
7/21/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
7/22/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
8/1/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
8/4/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
8/12/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/20/2025
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
10/20/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
10/20/2025
|
Approved
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
11/18/2025
|
Corrections Issued
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
1/23/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Final
|
4/1/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
4/1/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Green Building Final
|
4/1/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
4/1/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Reinforced Masonry Frame
|
4/1/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
4/1/2026
|
SGSOV Not Ready
|
MARTIN TAVITIAN
|
|
Smoke Detectors
|
4/1/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Special/Order Compliance
|
5/5/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Final
|
5/20/2026
|
Partial Inspection
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
5/20/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Green Building Final
|
5/20/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
5/20/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Reinforced Masonry Frame
|
5/20/2026
|
Approved
|
MARTIN TAVITIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
5/20/2026
|
SGSOV Approved
|
MARTIN TAVITIAN
|
|
Smoke Detectors
|
5/20/2026
|
Conditional Approval
|
MARTIN TAVITIAN
|