13310 W BEAVER ST 91342

Certificate Information: 13310 W BEAVER ST 91342

Application / Permit
21010-10000-00743
Plan Check / Job No.
B21LA02717
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-plan: New one-story A.D.U.PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
CofO Issued on 11/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 CRYSTEL MAALOUF
Corrections Issued 3/12/2021 CRYSTEL MAALOUF
Quality Review Completed 3/15/2021 WING SUEN
Plan Check Approved 11/2/2021 CRYSTEL MAALOUF
Issued 11/8/2021 APPLICANT
CofO in Progress 11/8/2022 ARAM AVEDISIAN
Permit Finaled 11/12/2022 MICHAEL SMITH
CofO Issued 11/12/2022 MICHAEL SMITH
Permit Finaled 11/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/31/2021 GABRIEL ROBLES
Construction near power lines Cleared 5/18/2021 RIDWAN HARDY
Construction within easement Cleared 5/18/2021 RIDWAN HARDY
Low Impact Development Cleared 8/27/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/30/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/31/2021 CARLOS AGUILERA
Sewer availability Cleared 8/31/2021 CARLOS AGUILERA

Contact Information

Contractor C I D Builders And Developers Inc; Lic. No.: 958193-B       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/8/2021 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 12/20/2021 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/4/2022 Partial Approval JOHN HAYES
Footing/Foundation/Slab 1/4/2022 Partial Approval JOHN HAYES
Underground Mechanical 1/4/2022 Partial Approval JOHN HAYES
Footing/Foundation/Slab 1/7/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 1/11/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 1/13/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 3/2/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 3/2/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 3/2/2022 Not Ready for Inspection JOHN HAYES
HVAC-Rough 3/2/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 3/2/2022 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 3/2/2022 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 3/4/2022 No Access for Inspection JOHN HAYES
Wood Frame 3/4/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 3/9/2022 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 3/9/2022 Partial Inspection MICHEL ABAJAN
HVAC-Rough 3/9/2022 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 3/9/2022 Partial Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 3/9/2022 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/16/2022 Partial Approval JOHN HAYES
HVAC-Rough 3/16/2022 Corrections Issued JOHN HAYES
Interior/Exterior Lathing 3/16/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 3/16/2022 Partial Approval JOHN HAYES
Shower Pan 3/16/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 3/29/2022 Approved JOHN HAYES
Green Building Rough 3/29/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 3/29/2022 Approved JOHN HAYES
Verify Sprinkler Sign Off 3/29/2022 Approved JOHN HAYES
Insulation 4/5/2022 Corrections Issued JOHN HAYES
Insulation 4/11/2022 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 4/11/2022 Not Ready for Inspection JOHN HAYES
Insulation 4/14/2022 Approved JOHN HAYES
Drywall Nailing 4/28/2022 Approved JOHN HAYES
Interior/Exterior Lathing 4/28/2022 Approved JOHN HAYES
Sewer 7/12/2022 Approved ARAM AVEDISIAN
Underground Mechanical 7/12/2022 Partial Approval ARAM AVEDISIAN
Final 8/1/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/1/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 8/1/2022 Approved ARAM AVEDISIAN
Final 8/11/2022 Not Ready for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Approved DEANDRE HOFFMAN
Service/Power Release 8/11/2022 Not Ready for Inspection DEANDRE HOFFMAN
Final 8/18/2022 Corrections Issued ARAM AVEDISIAN
Final 8/24/2022 No Access for Inspection ARAM AVEDISIAN
Service/Power Release 8/24/2022 No Access for Inspection ARAM AVEDISIAN
Final 8/31/2022 Corrections Issued ARAM AVEDISIAN
Service/Power Release 8/31/2022 Not Required ARAM AVEDISIAN
Final 11/7/2022 OK to Issue CofO ARAM AVEDISIAN