4628 S COOLIDGE AVE 90230
Certificate Information: 4628 S COOLIDGE AVE 90230
- Application / Permit
- 21010-10000-00742
- Plan Check / Job No.
- B20LA24411
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached ADU (2-Story) PER ORDINANCE
- Permit Issued
- Issued on 12/12/2021
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | CARLOS MONTES |
| Corrections Issued | 2/20/2021 | CARLOS MONTES |
| Quality Review Completed | 3/5/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 9/14/2021 | CARLOS MONTES |
| Plan Check Approved | 10/19/2021 | CARLOS MONTES |
| Issued | 12/12/2021 | APPLICANT |
| CofO in Progress | 10/18/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 10/24/2023 | DANIEL ORRANTE |
| CofO Issued | 10/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/13/2021 | PETE EYRE |
| Address approval | Cleared | 4/20/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 5/20/2021 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 5/24/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 7/15/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/21/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | H C L Group Inc; Lic. No.: 1052561-B | 4500 PARK GRANADA BLVD 202 CALABASAS, CA 91302 |
| Engineer | Askarian,, Soroosh Namaghi; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/26/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/2/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Conditional Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 11/23/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/4/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/14/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/23/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 2/23/2023 | Approved | JESUS RODRIGUEZ |
| MERV13>=Rough | 2/23/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 2/23/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/23/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Insulation | 3/3/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/3/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/13/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/18/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 9/18/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/18/2023 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/18/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/3/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/3/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/3/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/6/2023 | Partial Approval | JESUS RODRIGUEZ |
| Final | 10/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/6/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 10/6/2023 | Approved | JESUS RODRIGUEZ |
| MERV13>=Final | 10/6/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 10/6/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 10/6/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | JESUS RODRIGUEZ |
| Final | 10/18/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Service/Power Release | 10/18/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/18/2023 | Approved | JESUS RODRIGUEZ |