5909-5913 S CRENSHAW BLVD 90043
Certificate Information: 5909-5913 S CRENSHAW BLVD 90043
- Application / Permit
- 21010-10000-00740
- Plan Check / Job No.
- B21LA02706
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- NEW 65 UNIT, 5-STORY (4-STORY TYPE V-A ON TOP OF GROUND FLOOR TYPE I-A ) INCLUDING 9 VERY LOW INCOME UNITS & 1 EXTREMELY LOW INCOME UNIT PER 12.22.A.31 (TOC).
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Valley
- Current Status
- Issued on 8/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/4/2021 | APPLICANT |
| Green Plans Picked Up | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | JOHNNY WU |
| Corrections Issued | 6/23/2021 | JOHNNY WU |
| Quality Review Completed | 6/25/2021 | FARUK SEZER |
| Applicant returned to address corrections | 4/4/2023 | JOHNNY WU |
| Applicant returned to address corrections | 4/6/2023 | JOHNNY WU |
| Applicant returned to address corrections | 4/18/2023 | JOHNNY WU |
| Applicant returned to address corrections | 7/11/2023 | JOHNNY WU |
| Applicant returned to address corrections | 7/18/2023 | JOHNNY WU |
| Applicant returned to address corrections | 9/12/2023 | JOHNNY WU |
| Applicant returned to address corrections | 9/13/2023 | JOHNNY WU |
| Applicant returned to address corrections | 9/20/2023 | JOHNNY WU |
| Applicant returned to address corrections | 9/22/2023 | JOHNNY WU |
| Applicant returned to address corrections | 9/27/2023 | JOHNNY WU |
| Applicant returned to address corrections | 12/4/2023 | JOHNNY WU |
| Plan Check Approved | 12/4/2023 | JOHNNY WU |
| Issued | 8/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 3/22/2023 | KURT CORRAL |
| Highway dedication | Cleared | 3/28/2023 | WALLIE JONG |
| Permit | Cleared | 3/28/2023 | WALLIE JONG |
| Driveway location | Cleared | 5/11/2023 | SEGAL ISMAEL |
| Fire Marshall Fire Life Safety | Cleared | 7/5/2023 | PEJMAN NOORI |
| Building over 36-ft | Cleared | 7/11/2023 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 7/19/2023 | JOHNNY WU |
| Low Impact Development | Cleared | 8/25/2023 | JORGE MEJIA LEMUS |
| Density Bonus 12.22.A.31 | Cleared | 8/29/2023 | DORIS KWOK |
| Roof/Waste drainage to street | Cleared | 8/29/2023 | WALLIE JONG |
| Green Code | Cleared | 9/28/2023 | AARON COSTA |
| "D" conditions | Cleared | 9/29/2023 | NATHAN ROMINE |
| Comm Cor/Mini-Mall | Cleared | 9/29/2023 | NATHAN ROMINE |
| Comm Cor/Mini-Mall | Cleared | 9/29/2023 | NATHAN ROMINE |
| Frnt yard landscape/Water mgmt | Cleared | 9/29/2023 | NATHAN ROMINE |
| Opn space landscape/Water mgmt | Cleared | 9/29/2023 | NATHAN ROMINE |
| Specific Plan | Cleared | 9/29/2023 | NATHAN ROMINE |
| Specific Plan | Cleared | 9/29/2023 | NATHAN ROMINE |
| ZA Case | Cleared | 9/29/2023 | NATHAN ROMINE |
| ZA Case | Cleared | 9/29/2023 | NATHAN ROMINE |
| ZI | Cleared | 9/29/2023 | NATHAN ROMINE |
| ZI | Cleared | 9/29/2023 | NATHAN ROMINE |
| Historic Resource Verification | Cleared | 10/11/2023 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 10/12/2023 | YASMINE BASHIRI |
| DAS Clearance | Cleared | 10/19/2023 | ELIZABETH TOMS |
| Metro Rail approval | Cleared | 11/8/2023 | JENNIFER SU |
| Sewer availability | Cleared | 11/29/2023 | WALLIE JONG |
| Hold | Cleared | 1/8/2026 | CARMEN MERAZ |
Contact Information
| Contractor | L E Construction & Development Inc; Lic. No.: 1051866-B | 7111 SANTA MONICA BLVD SUITE B-272 WEST HOLLYWOOD, CA 90046 |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: C38454 | 17337 VENTURA BLVD STE 112 ENCINO, CA 91316 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/29/2025 | Not Ready for Inspection | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 11/1/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/1/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 1/12/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/22/2026 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 1/22/2026 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 1/28/2026 | Partial Approval | JAMES POWERS |
| Pre-Inspection | 2/2/2026 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 2/3/2026 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 2/5/2026 | Not Ready for Inspection | JAMES POWERS |
| Special/Order Compliance | 2/5/2026 | Partial Inspection | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 2/6/2026 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 2/9/2026 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 3/2/2026 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 3/3/2026 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 3/13/2026 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 3/17/2026 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 3/24/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 3/26/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 3/31/2026 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 3/31/2026 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 4/1/2026 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 4/7/2026 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 4/23/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 4/24/2026 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 4/27/2026 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 5/1/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/4/2026 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 5/5/2026 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 5/6/2026 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Masonry | 5/8/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/11/2026 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/11/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 5/12/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/20/2026 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Masonry | 5/22/2026 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 5/26/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/26/2026 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 5/26/2026 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Masonry | 5/27/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/28/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/29/2026 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 6/3/2026 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 6/8/2026 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Masonry | 6/9/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/10/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/11/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/12/2026 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Masonry | 6/15/2026 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 6/16/2026 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 6/16/2026 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 6/22/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/23/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/30/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 7/6/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 7/22/2026 | Not Ready for Inspection | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 7/22/2026 | Not Ready for Inspection | JAMES POWERS |