117-117 3/4 E 29TH ST 90011

Certificate Information: 117-117 3/4 E 29TH ST 90011

Application / Permit
21010-10000-00731
Plan Check / Job No.
B21LA02668
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX WITH ADU (937 SF) PER 12.22 A33 C & E (REAR)
Permit Issued
Issued on 1/24/2023
Issuing Office
Current Status
CofO Issued on 6/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 STARR CHEN
Corrections Issued 2/20/2021 STARR CHEN
Quality Review Completed 2/22/2021 JASON HEALEY
Building Plans Picked Up 2/25/2021 APPLICANT
Applicant returned to address corrections 5/11/2022 STARR CHEN
Applicant returned to address corrections 6/28/2022 STARR CHEN
Applicant returned to address corrections 9/20/2022 STARR CHEN
Plan Check Approved 11/15/2022 STARR CHEN
Issued 1/24/2023 APPLICANT
CofO in Progress 5/23/2024 ALEJANDRO DE ARTOLA
CofO Issued 6/11/2024 DEROLD HAUFF
Permit Finaled 6/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/21/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/21/2022 JEANETTE VONG
Permit Cleared 1/21/2022 JEANETTE VONG
Frnt yard landscape/Water mgmt Cleared 2/4/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 2/11/2022 GILBERT URREA
Low Impact Development Cleared 2/28/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/2/2022 JEANETTE VONG
Sewer availability Cleared 3/3/2022 JEANETTE VONG
Trees in Parkway Cleared 3/23/2022 STARR CHEN
Tenant Habitability Plan Cleared 10/19/2022 MICHAEL SOTO

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Gemilyan Karen; Lic. No.: 801955-B 4606 WILLIS AVE #307      SHERMAN OAKS, CA 91403
Engineer Aboufadel,, Nicholas Fadlo; Lic. No.: C50588 4000 PARK NEWPORT SUITE 303      NEWPORT BEACH, CA 92660
Engineer Moughraby,, Ousama; Lic. No.: C91595 9611 1/2 OLIVE ST.      BELLFLOWER, CA 90706
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791
Landscape Architect Macias,, Jaime; Lic. No.: LA5870 953 FLORE STREET      ANAHEIM, CA 92802

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 1/26/2023 Corrections Issued SCOTT FINNILA
Underground Mechanical 1/26/2023 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 2/14/2023 Not Ready for Inspection BRENDAN MORELLI
METHANE-Barrier 2/14/2023 Not Ready for Inspection BRENDAN MORELLI
METHANE-Final 2/14/2023 Not Ready for Inspection BRENDAN MORELLI
METHANE-Subgrade 2/14/2023 Corrections Issued BRENDAN MORELLI
Deputy Reinf. Concrete 2/27/2023 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 3/2/2023 Partial Approval BRENDAN MORELLI
METHANE-Barrier 3/2/2023 Approved BRENDAN MORELLI
METHANE-Rough 3/2/2023 Approved BRENDAN MORELLI
METHANE-Subgrade 3/2/2023 Approved BRENDAN MORELLI
Footing/Foundation/Slab 3/8/2023 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 4/10/2023 No Access for Inspection BRENDAN MORELLI
Green Building Rough 4/10/2023 No Access for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 4/10/2023 No Access for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 4/14/2023 No Access for Inspection BRENDAN MORELLI
Green Building Rough 4/14/2023 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 4/14/2023 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 5/15/2023 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 5/15/2023 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Off-Hour Fees Due
PLUMBING-Rough 8/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Rough 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 9/20/2023 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 9/21/2023 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 9/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 9/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 9/28/2023 Approved ALEJANDRO DE ARTOLA
METHANE-Rough 9/28/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/5/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 10/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Rough 10/6/2023 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 10/6/2023 Approved ALEJANDRO DE ARTOLA
Insulation 10/11/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/11/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/16/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 10/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/23/2023 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/23/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/23/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/23/2023 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 10/26/2023 Corrections Issued ALEJANDRO DE ARTOLA
Shower Pan 10/31/2023 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/7/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 11/9/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/9/2023 Approved ENRIQUE MIRELES
Underground Mechanical 12/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 1/10/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 1/10/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 1/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/1/2024 Approved ALEJANDRO DE ARTOLA
Green Building Final 4/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 4/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/17/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/9/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/9/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/10/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/22/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 5/22/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/22/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 5/22/2024 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 5/22/2024 Approved ALEJANDRO DE ARTOLA