eplan. PROPOSED 1-STORY DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 2/1/2022
Issuing Office
Current Status
CofO Issued on 3/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 MICHAEL LOPEZ
Corrections Issued 4/12/2021 MICHAEL LOPEZ
Quality Review Completed 4/22/2021 WING SUEN
Applicant returned to address corrections 1/12/2022 MICHAEL LOPEZ
Plan Check Approved 1/13/2022 MICHAEL LOPEZ
Issued 2/1/2022 APPLICANT
CofO in Progress 12/13/2023 JAVIER RAMOS JR
Permit Finaled 3/1/2024 RUBEN SALAS
Permit Finaled 3/1/2024 RUBEN SALAS
CofO Issued 3/1/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/17/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/17/2021 CARLOS AGUILERA
Sewer availability Cleared 9/17/2021 CARLOS AGUILERA
Construction near power lines Cleared 11/8/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 12/9/2021 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/23/2022 Approved MICHAEL TEMPLE
Underground Mechanical 2/23/2022 Approved MICHAEL TEMPLE
Footing/Foundation/Slab 3/2/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/21/2022 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 3/21/2022 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 3/21/2022 Corrections Issued MICHAEL TEMPLE
Wood Frame 3/21/2022 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 4/5/2022 No Access for Inspection JAVIER RAMOS JR
HVAC-Rough 4/5/2022 No Access for Inspection JAVIER RAMOS JR
PLUMBING-Rough 4/5/2022 No Access for Inspection JAVIER RAMOS JR
Wood Frame 4/5/2022 No Access for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 4/8/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 4/8/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/8/2022 Approved JAVIER RAMOS JR
Wood Frame 4/8/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 5/10/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/10/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 5/10/2022 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 5/10/2022 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Rough 5/10/2022 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/10/2022 Approved JAVIER RAMOS JR
Insulation 5/13/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/13/2022 Approved JAVIER RAMOS JR
Drywall Nailing 5/18/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 5/23/2022 Approved RAUL OLAGI
Drywall Nailing 5/23/2022 Approved RAUL OLAGI
Green Building Rough 5/23/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/23/2022 Partial Approval RAUL OLAGI
Shower Pan 5/23/2022 Approved RAUL OLAGI
Final 8/24/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 8/24/2023 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Final 8/24/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 8/24/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 8/24/2023 Approved JAVIER RAMOS JR
Final 9/26/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/28/2023 Approved JAVIER RAMOS JR
Final 12/13/2023 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 12/13/2023 Approved JAVIER RAMOS JR