Green Building Rough
|
1/12/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Structural Steel Frame
|
1/12/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
1/12/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
2/23/2022
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
2/26/2022
|
Partial Approval
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
2/26/2022
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
3/5/2022
|
Partial Approval
|
KENNETH ROBERTS
|
|
Green Building Rough
|
3/11/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Structural Steel Frame
|
3/11/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
3/11/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
3/14/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
3/14/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
3/15/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
3/16/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
3/16/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/16/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
3/16/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
3/17/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
3/17/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/17/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
3/18/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
3/18/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/18/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
3/21/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
3/21/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/21/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
3/22/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
3/22/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/22/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/23/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/24/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/25/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
3/30/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
3/31/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/1/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/1/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
4/1/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
4/1/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Drywall Nailing
|
4/5/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Green Building Rough
|
4/5/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
4/5/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Structural Steel Frame
|
4/5/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
4/5/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/6/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/6/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/6/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/7/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/7/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/7/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/8/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/8/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/8/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
4/8/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/11/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Fireproofing
|
4/11/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
4/11/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Drywall Nailing
|
4/11/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
4/11/2022
|
No Access for Inspection
|
DANIEL VARNUM
|
|
Deputy Drilled-In Anchors
|
4/12/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/12/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/12/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/13/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/13/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/13/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/14/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/14/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/14/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
4/14/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
4/14/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/15/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/15/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/15/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/18/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/18/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
4/18/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/18/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/19/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/19/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
4/19/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/19/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/20/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/20/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/20/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/21/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
4/21/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
4/21/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
4/22/2022
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Fireproofing
|
4/22/2022
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Steel/Welding
|
4/22/2022
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Drilled-In Anchors
|
4/25/2022
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Fireproofing
|
4/25/2022
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Steel/Welding
|
4/25/2022
|
Conditional Approval
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
4/25/2022
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
4/25/2022
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
4/26/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Light Gage Steel Frame
|
4/29/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
5/2/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
5/4/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
5/9/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
5/9/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
5/9/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
5/10/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
5/10/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
5/10/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
5/10/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Interior/Exterior Lathing
|
5/10/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
5/11/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Fireproofing
|
5/11/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
5/11/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
5/11/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
5/12/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Fireproofing
|
5/12/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
5/12/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
5/12/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
5/13/2022
|
Conditional Approval
|
JOHN KITCKO
|
|
Deputy Fireproofing
|
5/13/2022
|
Conditional Approval
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
5/13/2022
|
Conditional Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
5/13/2022
|
Partial Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
5/13/2022
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Drilled-In Anchors
|
5/20/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
5/23/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
5/23/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
5/23/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/24/2022
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Footing/Foundation/Slab
|
5/24/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
5/25/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
5/25/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
6/8/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
6/14/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/14/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
6/14/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/16/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/17/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
6/21/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Insulation
|
6/21/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
6/21/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/29/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
6/29/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Insulation
|
7/19/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Interior/Exterior Lathing
|
7/19/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
7/19/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Grading Pre-Inspection
|
7/20/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Green Building Rough
|
8/17/2022
|
Approved
|
CAMERON CHABAN
|
|
Reinforced Concrete Frame
|
8/17/2022
|
Approved
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
8/17/2022
|
Approved
|
CAMERON CHABAN
|
|
Wall Anchors
|
8/17/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
T-Bar Ceiling
|
8/29/2022
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Light Gage Steel Frame
|
9/2/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
9/6/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
9/8/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Interior/Exterior Lathing
|
9/8/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
9/13/2022
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
9/15/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
T-Bar Ceiling
|
9/19/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
T-Bar Ceiling
|
9/21/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
Final
|
9/23/2022
|
Partial Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
9/23/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
9/23/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
9/23/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
SGSOV-Seismic Gas S/O Valve
|
9/23/2022
|
SGSOV Not Ready
|
JOHN KITCKO
|
|
Smoke Detectors
|
9/23/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Structural Steel Frame
|
9/23/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
9/27/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
9/28/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
10/4/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
10/4/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
10/11/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/12/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
T-Bar Ceiling
|
10/12/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
10/13/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/17/2022
|
Partial Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
10/24/2022
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
10/25/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
10/25/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
11/2/2022
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
11/2/2022
|
Approved
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
11/3/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
11/3/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Excavation/Setback/Form/Re-Bar
|
11/4/2022
|
Corrections Issued
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
11/15/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
11/16/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
11/17/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
11/18/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Interior/Exterior Lathing
|
11/18/2022
|
Approved
|
CAMERON CHABAN
|
|
Pre-Inspection
|
12/1/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
12/9/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Special/Order Compliance
|
12/12/2022
|
No Access for Inspection
|
DANIEL VARNUM
|
|
Special/Order Compliance
|
12/13/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Special/Order Compliance
|
12/16/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Green Building Final
|
12/21/2022
|
Approved
|
CAMERON CHABAN
|
|
Special/Order Compliance
|
12/21/2022
|
Corrections Issued
|
CAMERON CHABAN
|
|
Special/Order Compliance
|
12/27/2022
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
12/28/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Special/Order Compliance
|
12/29/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Special/Order Compliance
|
12/29/2022
|
Partial Inspection
|
JEFFREY DURAN
|
|
Special/Order Compliance
|
1/3/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Special/Order Compliance
|
1/26/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Final
|
9/7/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
9/7/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Reinforced Masonry Frame
|
9/7/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
SGSOV-Seismic Gas S/O Valve
|
9/7/2023
|
SGSOV Not Ready
|
CAMERON CHABAN
|
|
Smoke Detectors
|
9/7/2023
|
Approved
|
CAMERON CHABAN
|
|
Structural Steel Frame
|
9/7/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Final
|
9/29/2023
|
OK to Issue CofO
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
9/29/2023
|
Approved
|
CAMERON CHABAN
|
|
Reinforced Masonry Frame
|
9/29/2023
|
Approved
|
CAMERON CHABAN
|
|
SGSOV-Seismic Gas S/O Valve
|
9/29/2023
|
SGSOV Approved
|
CAMERON CHABAN
|
|
Structural Steel Frame
|
9/29/2023
|
Approved
|
CAMERON CHABAN
|