620 E 249TH ST 90744
Certificate Information: 620 E 249TH ST 90744
- Application / Permit
- 21010-10000-00709
- Plan Check / Job No.
- B21LA02530
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) Charter School - middle
- Work Description
- CONSTRUCTION OF A NEW 2-STORY, 12807 SF EDUCATIONAL BUILDING FOR AN EXISTING CHARTER MIDDLE SCHOOL. 1 OF 2
- Permit Issued
- Issued on 3/4/2022
- Issuing Office
- Current Status
- CofO Issued on 4/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | JOHNNY WU |
| Plans on Hold | 2/18/2021 | BILL STUTSMAN |
| Green Plans Picked Up | 3/9/2021 | APPLICANT |
| Hold Released | 4/8/2021 | BILL STUTSMAN |
| Corrections Issued | 4/20/2021 | JOHNNY WU |
| Quality Review Completed | 4/22/2021 | FARUK SEZER |
| Disabled Access Plans Picked Up | 5/17/2021 | APPLICANT |
| Applicant returned to address corrections | 5/21/2021 | JOHNNY WU |
| Applicant returned to address corrections | 9/16/2021 | JOHNNY WU |
| Applicant returned to address corrections | 9/24/2021 | JOHNNY WU |
| Applicant returned to address corrections | 11/16/2021 | JOHNNY WU |
| Applicant returned to address corrections | 1/4/2022 | JOHNNY WU |
| Plan Check Approved | 2/28/2022 | JOHNNY WU |
| Issued | 3/4/2022 | APPLICANT |
| Building Plans Picked Up | 3/7/2022 | APPLICANT |
| TCO Issued (Expire Date: 02-25-2023) | 8/29/2022 | DAVID TSAU |
| TCO Issued (Expire Date: 09-20-2023) | 3/24/2023 | HENRY BAGHDASSARIAN |
| CofO in Progress | 4/5/2023 | JOEY BUCHANAN |
| Permit Finaled | 4/5/2023 | DAVID TSAU |
| CofO Issued | 4/5/2023 | DAVID TSAU |
| Permit Finaled | 4/5/2023 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2021 | CHINH DINH |
| Methane Ordinance | Cleared | 5/21/2021 | ANDREW KO |
| Sewer availability | Cleared | 6/22/2021 | CHINH DINH |
| Hydrant and Access approval | Cleared | 7/20/2021 | MATTHEW CRAIG |
| Comm Cor/Mini-Mall | Cleared | 11/4/2021 | NOAH MCCOY |
| Comm Cor/Mini-Mall | Cleared | 11/4/2021 | NOAH MCCOY |
| Prkng lot landscape/Water mgmt | Cleared | 11/4/2021 | NOAH MCCOY |
| ZA Case | Cleared | 11/4/2021 | NOAH MCCOY |
| Green Code | Cleared | 11/16/2021 | RAHEL BEYENE |
| Highway dedication | Cleared | 11/16/2021 | ERIK BEASLEY |
| Low Impact Development | Cleared | 12/1/2021 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 12/3/2021 | ERIK BEASLEY |
| Fire Marshal Fire Life Safety | Cleared | 12/16/2021 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 1/6/2022 | EDDIE GARIN |
| CPC | Cleared | 2/10/2022 | NOAH MCCOY |
| Miscellaneous | Cleared | 2/10/2022 | NOAH MCCOY |
| ZI | Cleared | 2/10/2022 | NOAH MCCOY |
Contact Information
| Architect | Palmer,, Keith Stanton; Lic. No.: C11096 | 715 BAY HILL DRIVE NEWPORT BEACH, CA 92660 |
| Contractor | Del Amo Construction Inc; Lic. No.: 744458-B | 23840 MADISON STREET TORRANCE, CA 90505 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Engineer | Sepich,, John Edward; Lic. No.: C37509 | 4007 MCCULLOUGH AVE 469 SAN ANTONIO, TX 78212 |
| Engineer | Wang,, Guan; Lic. No.: C79702 | 135 N SAN GABRIEL BLVD SAN GABRIEL, CA 91775 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/8/2022 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 3/23/2022 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 3/25/2022 | Partial Approval | DAVID TSAU |
| METHANE-Subgrade | 3/25/2022 | Not Ready for Inspection | DAVID TSAU |
| Footing/Foundation/Slab | 4/8/2022 | Partial Approval | JOEY BUCHANAN |
| METHANE-Barrier | 4/8/2022 | Approved | JOEY BUCHANAN |
| METHANE-Subgrade | 4/8/2022 | Approved | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Partial Approval | JOEY BUCHANAN |
| Green Building Rough | 4/25/2022 | Approved | JOEY BUCHANAN |
| METHANE-Rough | 4/25/2022 | Approved | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 4/25/2022 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 4/26/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 4/26/2022 | Partial Approval | JOEY BUCHANAN |
| Deputy Wood Construction | 4/27/2022 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 4/28/2022 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 4/29/2022 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 5/4/2022 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 5/5/2022 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 5/6/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 5/6/2022 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 5/18/2022 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 5/25/2022 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 6/1/2022 | Approved | JOEY BUCHANAN |
| Masonry Wall/Backfill | 6/3/2022 | Partial Approval | JOEY BUCHANAN |
| Masonry Wall/Backfill | 6/7/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 6/9/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 6/10/2022 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 7/6/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 7/12/2022 | Conditional Approval | JOEY BUCHANAN |
| Posting Pre-Inspection | 7/14/2022 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 7/27/2022 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 8/2/2022 | Partial Inspection | DAVID TSAU |
| Final | 8/9/2022 | Partial Inspection | DAVID TSAU |
| Green Building Final | 8/9/2022 | Partial Approval | DAVID TSAU |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Not Ready | DAVID TSAU |
| Smoke Detectors | 8/9/2022 | Partial Approval | DAVID TSAU |
| Wood Frame | 8/9/2022 | Partial Approval | DAVID TSAU |
| Special/Order Compliance | 8/10/2022 | Approved | DAVID TSAU |
| Final | 8/11/2022 | Partial Inspection | DAVID TSAU |
| Green Building Final | 8/11/2022 | Approved | DAVID TSAU |
| SGSOV-Seismic Gas S/O Valve | 8/11/2022 | SGSOV Not Ready | DAVID TSAU |
| Smoke Detectors | 8/11/2022 | Approved | DAVID TSAU |
| Wood Frame | 8/11/2022 | Not Ready for Inspection | DAVID TSAU |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | JOEY BUCHANAN |
| Final | 8/25/2022 | Conditional Approval | JOEY BUCHANAN |
| Wood Frame | 8/25/2022 | Approved | JOEY BUCHANAN |
| Final | 8/29/2022 | Corrections Issued | JOEY BUCHANAN |
| Final | 1/6/2023 | Partial Inspection | AMANUEL BERHE |
| Special/Order Compliance | 2/1/2023 | Approved | JOEY BUCHANAN |
| Final | 2/2/2023 | Conditional Approval | JOEY BUCHANAN |