10990 N EL DORADO AVE 91331

Certificate Information: 10990 N EL DORADO AVE 91331

Application / Permit
21010-10000-00693
Plan Check / Job No.
B21LA02477
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. New 39 ft. x 28 ft. , 1-story, detached Accessory Dwelling Unit PER LAMC 12.22 A.33 (c) AND (d)
Permit Issued
Issued on 11/23/2021
Issuing Office
Current Status
CofO Issued on 4/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 CRYSTEL MAALOUF
Corrections Issued 3/12/2021 CRYSTEL MAALOUF
Quality Review Completed 3/16/2021 WING SUEN
Plan Check Approved 11/16/2021 CRYSTEL MAALOUF
Issued 11/23/2021 APPLICANT
CofO in Progress 4/27/2023 MICHEL ABAJAN
CofO Issued 4/27/2023 MICHAEL SMITH
Permit Finaled 4/27/2023 MICHAEL SMITH

Permit Application Clearance Information

Clean Up Green Up Cleared 4/20/2021 DANG NGUYEN
Address approval Cleared 4/27/2021 GABRIEL ROBLES
Sewer availability Cleared 5/3/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 6/9/2021 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 8/23/2021 GABRIEL ROBLES
Low Impact Development Cleared 9/4/2021 TA ANH
Roof/Waste drainage to street Cleared 9/8/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2022 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 2/22/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 2/22/2022 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 3/2/2022 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 3/22/2022 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 3/25/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/31/2022 Partial Approval MICHEL ABAJAN
MERV13>=Rough 3/31/2022 Partial Inspection MICHEL ABAJAN
METHANE-Rough 3/31/2022 Partial Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 3/31/2022 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval MICHEL ABAJAN
MERV13>=Rough 4/5/2022 Approved MICHEL ABAJAN
METHANE-Rough 4/5/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/5/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Partial Approval MICHEL ABAJAN
HVAC-Rough 6/28/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 6/28/2022 Partial Approval GREGG CUMMINGS
Underground Mechanical 7/13/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 7/27/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/1/2022 Approved MICHEL ABAJAN
Green Building Rough 8/1/2022 Approved MICHEL ABAJAN
HVAC-Rough 8/1/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/9/2022 Partial Approval DEANDRE HOFFMAN
Insulation 8/16/2022 Approved MICHEL ABAJAN
Drywall Nailing 8/23/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/23/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 11/29/2022 Corrections Issued MICHEL ABAJAN
Final 11/29/2022 Corrections Issued MICHEL ABAJAN
HVAC-Final 11/29/2022 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Final 11/29/2022 Approved MICHEL ABAJAN
PLUMBING-Final 11/29/2022 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 11/29/2022 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 11/29/2022 Not Ready for Inspection MICHEL ABAJAN
Final 3/22/2023 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 3/22/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 3/22/2023 Approved MICHEL ABAJAN
Final 4/4/2023 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 4/4/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 4/20/2023 Approved MICHEL ABAJAN
Final 4/20/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 4/20/2023 Approved MICHEL ABAJAN
PLUMBING-Final 4/20/2023 Approved MICHEL ABAJAN
Service/Power Release 4/20/2023 Not Ready for Inspection MICHEL ABAJAN
Final 4/26/2023 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 4/26/2023 Approved MICHEL ABAJAN