3130 N DORCHESTER AVE 90032
Certificate Information: 3130 N DORCHESTER AVE 90032
- Application / Permit
- 21010-10000-00687
- Plan Check / Job No.
- B21LA02398
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- PROPOSED 1-CAR GARAGE AT REAR OF LOT. CONSTRUCTION PER W.F.P.P. (2 OF 2)
- Permit Issued
- Issued on 12/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/23/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/14/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 12/13/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 12/15/2022 | GEORGE ALVAREZ |
| Issued | 12/23/2022 | APPLICANT |
| CofO in Progress | 5/9/2024 | LILIANA PORTILLO |
| CofO Issued | 5/15/2024 | DEROLD HAUFF |
| Permit Finaled | 5/15/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/16/2021 | BRIAN MILLER |
| Construction near power lines | Cleared | 3/21/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | AMY COLIN |
| Deputy Other (see comments) | 2/22/2023 | Conditional Approval | AMY COLIN |
| Footing/Foundation/Slab | 2/27/2023 | Approved | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Approved | RUBEN SALAS |
| Green Building Rough | 3/9/2023 | Not Ready for Inspection | RUBEN SALAS |
| Wood Frame | 3/9/2023 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Rough | 3/16/2023 | Approved | AMY COLIN |
| Wood Frame | 3/16/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 3/24/2023 | Partial Approval | AMY COLIN |
| Insulation | 5/1/2023 | Approved | AMY COLIN |
| Drywall Nailing | 5/10/2023 | Approved | RUBEN SALAS |
| Final | 11/17/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 11/17/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/17/2023 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 11/17/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 5/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 5/7/2024 | Approved | LILIANA PORTILLO |
| Final | 5/8/2024 | OK to Issue CofO | LILIANA PORTILLO |