13002 S MENLO AVE 90247

Certificate Information: 13002 S MENLO AVE 90247

Application / Permit
21010-10000-00669
Plan Check / Job No.
B21LA02348
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-plan: PROPOSED GROUND FLOOR ADDITION AND SECOND FLOOR ADDITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE. EXISTING 2-CAR GARAGE TO REMAIN.
Permit Issued
Issued on 11/21/2023
Issuing Office
Current Status
CofO Issued on 3/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/24/2021 MICHAEL LOPEZ
Corrections Issued 3/5/2021 MICHAEL LOPEZ
Quality Review Completed 3/10/2021 HERNAN ARREOLA
Applicant returned to address corrections 1/26/2023 MICHAEL LOPEZ
Applicant returned to address corrections 2/22/2023 MICHAEL LOPEZ
Applicant returned to address corrections 6/14/2023 MICHAEL LOPEZ
Applicant returned to address corrections 8/4/2023 MICHAEL LOPEZ
Applicant returned to address corrections 9/1/2023 MICHAEL LOPEZ
Applicant returned to address corrections 9/15/2023 MICHAEL LOPEZ
Applicant returned to address corrections 10/18/2023 MICHAEL LOPEZ
Plan Check Approved 11/9/2023 MICHAEL LOPEZ
Issued 11/21/2023 APPLICANT
CofO in Progress 3/5/2026 JOSEPH MCGARRY
Permit Finaled 3/9/2026 ANSON MAGLASANG
Permit Finaled 3/9/2026 ANSON MAGLASANG
CofO Issued 3/9/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 6/21/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 8/5/2021 JOSE HERNANDEZ
ZA Case Cleared 8/5/2021 ANACANY HURTADO
Sewer availability Cleared 8/6/2021 JOSE HERNANDEZ
Hydrant and Access approval Cleared 8/31/2021 KURT CORRAL
Low Impact Development Cleared 5/16/2023 TOMMY YIN
Permit Cleared 8/8/2023 KHAING AYE
Roof/Waste drainage to street Cleared 8/8/2023 KHAING AYE

Contact Information

Architect Reindersma,, Sake Harm; Lic. No.: C19346 7929 E CAMINO REAL      SCOTTSDALE, AZ 85255
Contractor Frisco Investment Group Inc; Lic. No.: 1038932-B       ,
Contractor M & M Design And Construction; Lic. No.: 1038932-B       ,
Engineer Bixler,, William David; Lic. No.: C90086 15150 N HAYDEN RD STE 220      SCOTTSDALE, AZ 85260

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/23/2024 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 1/23/2024 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 1/23/2024 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 1/24/2024 Partial Approval JAMES CHAVEZ
METHANE-Barrier 3/19/2024 Not Ready for Inspection JAMES CHAVEZ
METHANE-Subgrade 3/19/2024 Approved JAMES CHAVEZ
Deputy Methane Barrier 3/20/2024 Conditional Approval JAMES CHAVEZ
Footing/Foundation/Slab 3/21/2024 Corrections Issued JAMES CHAVEZ
METHANE-Barrier 3/21/2024 Approved JAMES CHAVEZ
Footing/Foundation/Slab 3/26/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 3/26/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Final 3/26/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Final 3/27/2024 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Corrections Issued JAMES CHAVEZ
Green Building Rough 4/15/2024 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 4/15/2024 Not Ready for Inspection JAMES CHAVEZ
METHANE-Rough 4/15/2024 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 6/17/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Not Ready for Inspection BEN MOLSTAD
Gas Test 12/4/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 12/4/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 12/4/2024 Not Ready for Inspection BEN MOLSTAD
Deputy Wood Construction 12/5/2024 Conditional Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/5/2024 Partial Approval BEN MOLSTAD
Gas Test 12/11/2024 Corrections Issued BEN MOLSTAD
HVAC-Rough 12/11/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 12/11/2024 Approved BEN MOLSTAD
Gas Test 12/16/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 12/16/2024 Partial Approval BEN MOLSTAD
ELECTRICAL-Rough 12/17/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 12/24/2024 Approved ANSON MAGLASANG
HVAC-Rough 12/24/2024 Approved ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Approved BEN MOLSTAD
Insulation 1/17/2025 Approved BEN MOLSTAD
Drywall Nailing 1/28/2025 Approved BEN MOLSTAD
Sewer 8/26/2025 Approved BEN MOLSTAD
Gas Test 11/18/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 12/9/2025 Corrections Issued BEN MOLSTAD
Final 12/9/2025 Corrections Issued BEN MOLSTAD
HVAC-Final 12/9/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Final 12/9/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 12/12/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 12/12/2025 Approved BEN MOLSTAD
PLUMBING-Final 12/12/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 1/5/2026 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Final 2/17/2026 Corrections Issued ARTHUR NEGRETE
ELECTRICAL-Final 2/18/2026 Approved JOSEPH MCGARRY
Final 3/2/2026 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 3/2/2026 Approved JOSEPH MCGARRY
METHANE-Final 3/2/2026 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 3/2/2026 Approved JOSEPH MCGARRY
Smoke Detectors 3/2/2026 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 3/4/2026 Approved JOSEPH MCGARRY
Final 3/4/2026 OK to Issue CofO JOSEPH MCGARRY
Footing/Foundation/Slab 3/4/2026 Approved JOSEPH MCGARRY
Green Building Rough 3/4/2026 Approved JOSEPH MCGARRY
MERV13>=Final 3/4/2026 Approved JOSEPH MCGARRY
MERV13>=Rough 3/4/2026 Approved JOSEPH MCGARRY
METHANE-Barrier 3/4/2026 Approved JOSEPH MCGARRY