8740 N SWINTON AVE 91343
Certificate Information: 8740 N SWINTON AVE 91343
- Application / Permit
- 21010-10000-00655
- Plan Check / Job No.
- B21LA02288
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached 1-story ADU.
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 4/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | JOE VO |
| Corrections Issued | 2/13/2021 | JOE VO |
| Quality Review Completed | 2/21/2021 | HERNAN ARREOLA |
| Plan Check Approved | 5/22/2021 | JOE VO |
| Issued | 6/10/2021 | APPLICANT |
| CofO in Progress | 4/3/2022 | RAUL OLAGI |
| Permit Finaled | 4/4/2022 | MICHAEL SMITH |
| CofO Issued | 4/4/2022 | MICHAEL SMITH |
| Permit Finaled | 4/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/25/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 4/15/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 4/30/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/16/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/21/2021 | Partial Inspection | JACK KARGODORIAN |
| Underground Mechanical | 6/21/2021 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 6/25/2021 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/25/2021 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2021 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 7/23/2021 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/27/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 7/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/30/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 7/30/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 7/30/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 8/2/2021 | Approved | JACK KARGODORIAN |
| Insulation | 8/2/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 8/2/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/3/2021 | Partial Approval | JACK KARGODORIAN |
| Insulation | 8/5/2021 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 8/9/2021 | Approved | DEANDRE HOFFMAN |
| HVAC-Rough | 8/9/2021 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/9/2021 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/11/2021 | Approved | JUSTIN HAWLEY |
| Final | 10/26/2021 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 10/26/2021 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Not Ready | RAUL OLAGI |
| Service/Power Release | 10/26/2021 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 10/26/2021 | Corrections Issued | RAUL OLAGI |
| Final | 1/18/2022 | Corrections Issued | RAUL OLAGI |
| Gas Test | 1/18/2022 | Approved | RAUL OLAGI |
| Green Building Final | 1/18/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/18/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 1/18/2022 | Approved | RAUL OLAGI |
| Final | 4/1/2022 | OK to Issue CofO | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/1/2022 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 4/1/2022 | Approved | RAUL OLAGI |