6440 W DREXEL AVE 90048
Certificate Information: 6440 W DREXEL AVE 90048
- Application / Permit
- 21010-10000-00642
- Plan Check / Job No.
- B21LA02267
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story single family dwelling w/ attached garage and basement (1 of 3). SEE COMMENTS
- Permit Issued
- Issued on 8/11/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 2/25/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 3/1/2021 | FARUK SEZER |
| Applicant returned to address corrections | 4/29/2021 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 6/17/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/15/2021 | SERGIO GUTIERREZ |
| No Progress | 8/3/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 8/3/2021 | SERGIO GUTIERREZ |
| Issued | 8/11/2021 | APPLICANT |
| Building Plans Picked Up | 8/18/2021 | APPLICANT |
| CofO in Progress | 9/14/2024 | MICHAEL PELHAM |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
| CofO Issued | 9/16/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/16/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 3/18/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2021 | JEANIE LAM |
| ZI | Cleared | 3/19/2021 | DANIEL CORONADO |
| Sewer availability | Cleared | 4/21/2021 | WALLIE JONG |
| GPI Written Notices | Cleared | 4/27/2021 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 4/27/2021 | SERGIO GUTIERREZ |
| Hydrant and Access approval | Cleared | 5/24/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 5/30/2021 | ANDRES COVARRUBIAS |
| Stormwater Pollution Mitigatn | Cleared | 5/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/4/2021 | JEANIE LAM |
Contact Information
| Contractor | Noesis Builders Inc; Lic. No.: 1046562-B | 8383 WILSHIRE BOULEVARD SUITE 740 BEVERLY HILLS, CA 90211 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
| Engineer | Krief,, Dan Dov; Lic. No.: C76041 | 6420 WILSHIRE BLVD STE 1000 LOS ANGELES, CA 90048 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/31/2021 | Approved | EVAN COOPER |
| Deputy Grading | 9/1/2021 | Conditional Approval | EVAN COOPER |
| Deputy Grading | 9/2/2021 | Conditional Approval | EVAN COOPER |
| Pre-Inspection | 9/2/2021 | Approved | EVAN COOPER |
| Deputy Grading | 9/3/2021 | Conditional Approval | EVAN COOPER |
| METHANE-Subgrade | 11/24/2021 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 12/20/2021 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 12/20/2021 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 12/20/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 12/20/2021 | Not Ready for Inspection | EVAN COOPER |
| Deputy Reinf. Concrete | 12/21/2021 | Conditional Approval | EVAN COOPER |
| METHANE-Barrier | 1/18/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/27/2022 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 2/19/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Other (see comments) | 2/22/2022 | Conditional Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 2/22/2022 | Conditional Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 2/22/2022 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 2/22/2022 | Partial Approval | EVAN COOPER |
| METHANE-Subgrade | 2/22/2022 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 2/28/2022 | Approved | EVAN COOPER |
| Masonry Wall/Backfill | 3/24/2022 | Corrections Issued | EVAN COOPER |
| Deputy Steel/Welding | 5/2/2022 | Conditional Approval | EVAN COOPER |
| Deputy Steel/Welding | 5/20/2022 | Conditional Approval | EVAN COOPER |
| Deputy Steel/Welding | 5/24/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Not Ready for Inspection | EVAN COOPER |
| Deputy Steel/Welding | 6/23/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 8/2/2022 | Conditional Approval | EVAN COOPER |
| Special/Order Compliance | 8/3/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 8/3/2022 | Partial Inspection | MICHAEL PELHAM |
| Deputy Wood Construction | 9/14/2022 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 9/28/2022 | Corrections Issued | EVAN COOPER |
| Deputy Drilled-In Anchors | 9/30/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Partial Approval | CLAYTON GRAHAM |
| Insulation | 11/16/2022 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 12/15/2022 | Corrections Issued | JEREMY TODD |
| Special/Order Compliance | 12/15/2022 | Partial Inspection | STEPHANIE SWANSON |
| Deputy Steel/Welding | 1/12/2023 | Partial Approval | JEREMY TODD |
| Deputy Reinf. Concrete | 3/13/2023 | Partial Approval | JEREMY TODD |
| ELECTRICAL-Rough | 3/13/2023 | Approved | JEREMY TODD |
| Shower Pan | 3/13/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 3/16/2023 | Approved | JEREMY TODD |
| Special/Order Compliance | 3/16/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 3/17/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 3/28/2023 | Corrections Issued | JEREMY TODD |
| Green Building Rough | 3/28/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 3/28/2023 | Approved | JEREMY TODD |
| Verify Sprinkler Sign Off | 3/28/2023 | Not Ready for Inspection | JEREMY TODD |
| Wood Frame | 3/28/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 3/30/2023 | Not Ready for Inspection | JEREMY TODD |
| Verify Sprinkler Sign Off | 3/30/2023 | Corrections Issued | JEREMY TODD |
| Interior/Exterior Lathing | 3/31/2023 | Corrections Issued | JEREMY TODD |
| Special/Order Compliance | 4/3/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/28/2023 | Not Ready for Inspection | EVAN COOPER |
| Grounding or Bonding | 5/2/2023 | No Access for Inspection | JEREMY TODD |
| Interior/Exterior Lathing | 5/2/2023 | Approved | JEREMY TODD |
| Special/Order Compliance | 5/2/2023 | Approved | JEREMY TODD |
| Insulation | 5/4/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 5/15/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 2/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Pool/Spa Cover | 2/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 5/22/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Service/Power Release | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 6/17/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 7/11/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 7/11/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Final | 7/22/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 7/25/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 8/16/2024 | Approved | MEL KHACHATOURIAN |
| Final | 8/16/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/16/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Final | 8/16/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 8/16/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 8/16/2024 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 8/16/2024 | Approved | MEL KHACHATOURIAN |
| Final | 8/26/2024 | OK to Issue CofO | MEL KHACHATOURIAN |