916 W 23RD ST 90007

Certificate Information: 916 W 23RD ST 90007

Application / Permit
21010-10000-00636
Plan Check / Job No.
B21LA02253
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU FOR MULTI-FAMILY PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) (1-STORY)
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2021 APPLICANT
Assigned to Plan Check Engineer 2/24/2021 CARLOS MONTES
Corrections Issued 3/3/2021 CARLOS MONTES
Quality Review Completed 3/10/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/24/2021 CARLOS MONTES
Applicant returned to address corrections 9/7/2021 CARLOS MONTES
Plan Check Approved 9/17/2021 CARLOS MONTES
Issued 9/23/2021 APPLICANT
CofO in Progress 4/15/2022 ALEJANDRO DE ARTOLA
Permit Finaled 4/28/2022 DEROLD HAUFF
CofO Issued 4/28/2022 DEROLD HAUFF
Permit Finaled 4/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/17/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/17/2021 JEANIE LAM
Sewer availability Cleared 3/17/2021 JEANIE LAM
HPOZ Cleared 4/15/2021 KATIE DEBIASE
"Q" conditions Cleared 4/22/2021 DANIEL CORONADO
Hydrant and Access approval Cleared 4/25/2021 KURT CORRAL
Low Impact Development Cleared 7/30/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/5/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Engineer Park,, Juntae; Lic. No.: NA65104       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/27/2021 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/4/2021 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Barrier 10/4/2021 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 10/4/2021 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/7/2021 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/7/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 10/8/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/12/2021 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/12/2021 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 10/13/2021 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/10/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/10/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 11/10/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/10/2021 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Rough 11/10/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/10/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 11/12/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/15/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 11/15/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 11/15/2021 Approved ALEJANDRO DE ARTOLA
Insulation 11/15/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 11/18/2021 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/18/2021 Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/1/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 12/2/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/23/2021 Approved ALEJANDRO DE ARTOLA
Final 12/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 12/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/23/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/23/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/23/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/23/2021 Approved ALEJANDRO DE ARTOLA
Final 1/31/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 1/31/2022 Approved ALEJANDRO DE ARTOLA
Final 4/14/2022 OK to Issue CofO ALEJANDRO DE ARTOLA