14570 1/2 W DICKENS ST 91403
Certificate Information: 14570 1/2 W DICKENS ST 91403
- Application / Permit
- 21010-10000-00629
- Plan Check / Job No.
- B21LA02232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 4 STORY SFD PER SMALL LOT SUBDIVISION (UNIT D) 4 OF 4
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Corrected on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 3/11/2022 | VU NGUYEN |
| Issued | 3/17/2022 | APPLICANT |
| CofO in Progress | 9/11/2024 | MISAEL ESPARZA |
| CofO Issued-Status Void | 9/25/2024 | DANIEL ORRANTE |
| Permit Finaled-Status Void | 9/25/2024 | DANIEL ORRANTE |
| Re-Activate Permit | 11/4/2024 | DANIEL ORRANTE |
| CofO Corrected | 1/16/2025 | RUBEN SALAS |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/25/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 11/2/2021 | KURT CORRAL |
| Miscellaneous | Cleared | 12/2/2021 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 12/2/2021 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 12/2/2021 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 12/2/2021 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 12/10/2021 | CHRIS PARK |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | DAGOVERTO GUERRERO |
| Frnt yard landscape/Water mgmt | Cleared | 1/20/2022 | RUBEN VASQUEZ |
| Highway dedication | Cleared | 2/16/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 2/16/2022 | CARLOS AGUILERA |
| Permit | Cleared | 2/16/2022 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 2/23/2022 | ADALBERTO VERA |
| Building over 36-ft | Cleared | 3/10/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 3/10/2022 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 3/10/2022 | VU NGUYEN |
| Construction near power lines | Cleared | 3/11/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/31/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/6/2022 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 6/7/2022 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 7/11/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2022 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 7/19/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 7/21/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 8/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 8/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 8/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 8/3/2022 | Conditional Approval | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 8/15/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 8/15/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 11/9/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 11/29/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/6/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 12/6/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 12/6/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 3/21/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 4/7/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 4/12/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 4/13/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/17/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/20/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 4/20/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/20/2023 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 4/20/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 4/25/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 4/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/11/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 5/11/2023 | Approved | WILLIAM WREN |
| Insulation | 5/19/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 6/1/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 6/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 10/19/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/27/2023 | Partial Inspection | MISAEL ESPARZA |
| Underground Mechanical | 10/27/2023 | Partial Approval | MISAEL ESPARZA |
| Masonry Wall/Backfill | 11/22/2023 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 2/2/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/21/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/11/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 4/25/2024 | Corrections Issued | MISAEL ESPARZA |
| Service/Power Release | 5/24/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 5/30/2024 | Approved | JOHN COLEMAN |
| Final | 6/24/2024 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/24/2024 | Approved | VINCENT HANLEY |
| Green Building Final | 6/24/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Not Required | VINCENT HANLEY |
| Smoke Detectors | 6/24/2024 | Approved | VINCENT HANLEY |
| Final | 9/6/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 9/11/2024 | OK to Issue CofO | MISAEL ESPARZA |