6601 1/2 N BERQUIST AVE 91307
Certificate Information: 6601 1/2 N BERQUIST AVE 91307
- Application / Permit
- 21010-10000-00620
- Plan Check / Job No.
- B21LA02188
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ADU PER ORDINANCE 186,481
- Permit Issued
- Issued on 6/8/2021
- Issuing Office
- Current Status
- CofO Issued on 6/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2021 | SINA KHOSRAVI |
| Corrections Issued | 2/21/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 2/24/2021 | APPLICANT |
| Applicant returned to address corrections | 5/6/2021 | TSE MING HUANG |
| Plan Check Approved | 5/17/2021 | TSE MING HUANG |
| Issued | 6/8/2021 | APPLICANT |
| CofO in Progress | 12/2/2021 | TROY SANDERS |
| CofO Issued | 6/4/2022 | MICHAEL SMITH |
| Permit Finaled | 6/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2021 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2021 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 2/25/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/25/2021 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 4/22/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/29/2021 | JORGE MEJIA LEMUS |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/14/2021 | Partial Approval | TROY SANDERS |
| Pre-Inspection | 7/14/2021 | Approved | TROY SANDERS |
| Sewer | 7/14/2021 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 7/14/2021 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 7/20/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 8/12/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 8/12/2021 | Approved | TROY SANDERS |
| Green Building Rough | 8/12/2021 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 8/12/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 8/12/2021 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 8/12/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/31/2021 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 8/31/2021 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 9/2/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/2/2021 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 9/2/2021 | Approved | STEPHANIE SWANSON |
| Insulation | 9/13/2021 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 9/16/2021 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 9/24/2021 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 9/24/2021 | Approved | STEPHANIE SWANSON |
| Sewer | 11/5/2021 | Not Ready for Inspection | TROY SANDERS |
| Sewer | 11/9/2021 | Approved | TROY SANDERS |
| Underground Mechanical | 11/9/2021 | Partial Approval | TROY SANDERS |
| Final | 11/16/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 11/16/2021 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Not Ready | TROY SANDERS |
| Service/Power Release | 11/16/2021 | Corrections Issued | TROY SANDERS |
| Smoke Detectors | 11/16/2021 | Approved | TROY SANDERS |
| Final | 12/2/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 12/2/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 12/2/2021 | Approved | TROY SANDERS |
| Special/Order Compliance | 12/30/2021 | Corrections Issued | TROY SANDERS |