2861 S SHENANDOAH ST 90034

Certificate Information: 2861 S SHENANDOAH ST 90034

Application / Permit
21010-10000-00613
Plan Check / Job No.
B20LA24408
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** New 44'x 23' 8" State-Approved Manufactured ADU on State-Approved Permanent Foundation.
Permit Issued
Issued on 10/29/2021
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 CRYSTEL MAALOUF
Corrections Issued 3/25/2021 CRYSTEL MAALOUF
Quality Review Completed 3/30/2021 MINYE PAK
Applicant returned to address corrections 6/1/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 7/21/2021 CRYSTEL MAALOUF
Plan Check Approved 10/26/2021 CRYSTEL MAALOUF
Issued 10/29/2021 APPLICANT
CofO in Progress 4/12/2022 JOHNNY MIRANDA
No Progress 4/13/2022 KENNETH NAGLE
CofO in Progress 4/13/2022 KENNETH NAGLE
CofO in Progress 4/18/2022 EVAN COOPER
Permit Finaled 4/25/2022 DANIEL ORRANTE
CofO Issued 4/25/2022 DANIEL ORRANTE
Permit Finaled 4/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/21/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/21/2021 RENZ SORIANO
Specific Plan Cleared 7/20/2021 EILEEN HUNT
Sewer availability Cleared 8/11/2021 RENZ SORIANO
ZI Cleared 8/11/2021 DYLAN SITTIG
Roof/Waste drainage to street Cleared 9/3/2021 THOMAS LANG
Hydrant and Access approval Cleared 9/11/2021 JOHN CONNEALLY
Miscellaneous Cleared 9/16/2021 CRYSTEL MAALOUF
Low Impact Development Cleared 10/8/2021 KHAING AYE
Miscellaneous Cleared 10/21/2021 CRYSTEL MAALOUF

Contact Information

Contractor Nordling Installs Manufactured Homes; Lic. No.: 1045282-C47 P O BOX 178      CARPINTERIA, CA 93014
Engineer Frolenko,, Gary; Lic. No.: C27863 23 HITCHCOCK WAY #104      SANTA BARBARA, CA 93105

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/18/2021 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 11/24/2021 Partial Approval EVAN COOPER
Footing/Foundation/Slab 11/24/2021 Partial Approval EVAN COOPER
Footing/Foundation/Slab 1/4/2022 Approved EVAN COOPER
ELECTRICAL-Rough 1/26/2022 Not Ready for Inspection EVAN COOPER
Sewer 1/26/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 3/2/2022 Approved EVAN COOPER
Final 3/2/2022 Corrections Issued EVAN COOPER
MERV13>=Final 3/2/2022 Approved EVAN COOPER
MERV13>=Rough 3/2/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Approved EVAN COOPER
Service/Power Release 3/2/2022 Approved EVAN COOPER
Smoke Detectors 3/2/2022 Approved EVAN COOPER
Verify Sprinkler Sign Off 3/2/2022 Approved EVAN COOPER
Final 4/11/2022 Conditional Approval JOHNNY MIRANDA
Final 4/12/2022 OK to Issue CofO EVAN COOPER