15532 W BOWDOIN ST 90272
Certificate Information: 15532 W BOWDOIN ST 90272
- Application / Permit
- 21010-10000-00591
- Plan Check / Job No.
- B21LA02116
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1. NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT AT BACK PROPERTY PER LAMC. 12.22 A.33 (c)AND(d)
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 2/17/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 2/18/2021 | FARUK SEZER |
| Applicant returned to address corrections | 8/11/2021 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 9/30/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 10/27/2021 | SERGIO GUTIERREZ |
| Issued | 12/9/2021 | APPLICANT |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| CofO in Progress | 4/12/2023 | BRENDAN LOONEY |
| Permit Finaled | 4/14/2023 | DANIEL ORRANTE |
| CofO Issued | 4/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 2/18/2021 | DENZEL HENDERSON |
| Address approval | Cleared | 2/24/2021 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2021 | CATHERINE ADROVER |
| Sewer availability | Cleared | 3/1/2021 | CATHERINE ADROVER |
| GPI Written Notices | Cleared | 3/12/2021 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 3/12/2021 | SERGIO GUTIERREZ |
| Hydrant and Access approval | Cleared | 7/6/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 9/17/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/20/2021 | CATHERINE ADROVER |
Contact Information
| Contractor | A G Builders & Development Corp; Lic. No.: 959503-B | 5530 CORBIN AVE SUITE #250 TARZANA, CA 91356 |
| Engineer | Lee,, Jack C; Lic. No.: L8407 | 576 E LAMBERT RD BREA, CA 92821 |
| Engineer | Sin,, John P; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/19/2022 | Approved | ANDREW NAVE |
| Sewer | 1/27/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 2/2/2022 | Approved | ANDREW NAVE |
| Sewer | 2/2/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2022 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 6/10/2022 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Approved | ANDREW NAVE |
| Rough-Elec/Plmb/HVAC | 6/22/2022 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 7/7/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 7/7/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 7/7/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 7/11/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 7/11/2022 | Approved | JUAN VALENZUELA |
| Shower Pan | 7/11/2022 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 7/11/2022 | Corrections Issued | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/19/2022 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 7/20/2022 | Corrections Issued | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 7/20/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/25/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/28/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/1/2022 | Approved | BRENDAN LOONEY |
| Insulation | 8/3/2022 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 8/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| Drywall Nailing | 8/10/2022 | Corrections Issued | BRENDAN LOONEY |
| Drywall Nailing | 8/17/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 8/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 8/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 8/29/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 9/7/2022 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 9/23/2022 | Approved | ANDREW NAVE |
| Final | 3/16/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 3/16/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 3/16/2023 | SGSOV Not Ready | BRENDAN LOONEY |
| Service/Power Release | 3/16/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 3/16/2023 | Approved | BRENDAN LOONEY |
| Final | 3/24/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 3/24/2023 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 3/24/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Service/Power Release | 3/31/2023 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 3/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/4/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 4/4/2023 | Approved | BRENDAN LOONEY |
| Service/Power Release | 4/4/2023 | Approved | BRENDAN LOONEY |
| Final | 4/12/2023 | OK to Issue CofO | BRENDAN LOONEY |