6829 W LELAND WAY 90028

Certificate Information: 6829 W LELAND WAY 90028

Application / Permit
21010-10000-00588
Plan Check / Job No.
B21LA02110
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c)-(d)
Permit Issued
Issued on 10/8/2021
Issuing Office
Current Status
CofO Issued on 8/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 DANIEL YIP
Corrections Issued 3/10/2021 DANIEL YIP
Quality Review Completed 3/10/2021 JASON HEALEY
Building Plans Picked Up 3/19/2021 APPLICANT
Applicant returned to address corrections 9/22/2021 DANIEL YIP
Plan Check Approved 10/4/2021 DANIEL YIP
Issued 10/8/2021 APPLICANT
CofO in Progress 7/20/2023 BRIAN SULLIVAN
Permit Finaled 8/28/2023 DEROLD HAUFF
CofO Issued 8/28/2023 DEROLD HAUFF
Permit Finaled 8/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/31/2021 CELINA MORENO
Historic monument Cleared 4/29/2021 MICAELA TORRES-GIL
Historic monument Cleared 4/29/2021 MICAELA TORRES-GIL
Frnt yard landscape/Water mgmt Cleared 5/10/2021 KENTON TRINH
Address approval Cleared 5/18/2021 CELINA MORENO
Sewer availability Cleared 5/18/2021 CELINA MORENO
Redevelopment Project Area Cleared 5/24/2021 DAVID URITA
Trees in Parkway Cleared 5/26/2021 JOHN KIM
Low Impact Development Cleared 8/16/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/20/2021 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/12/2021 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/7/2021 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 12/7/2021 Not Ready for Inspection BRIAN SULLIVAN
Sewer 12/7/2021 Corrections Issued BRIAN SULLIVAN
Underground Mechanical 12/7/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 12/8/2021 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Partial Approval BRIAN SULLIVAN
Green Building Rough 2/1/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 2/1/2022 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 2/17/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 3/23/2022 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 3/23/2022 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval STUART CHAPMAN
Deputy Wood Construction 6/1/2022 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 7/29/2022 Conditional Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 7/29/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 8/3/2022 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 8/3/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/10/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 8/10/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 8/10/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 8/19/2022 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 8/19/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/23/2022 Approved BRIAN SULLIVAN
Drywall Nailing 9/16/2022 Approved BRIAN SULLIVAN
Insulation 9/16/2022 Approved BRIAN SULLIVAN
Shower Pan 9/16/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/30/2022 Approved BRIAN SULLIVAN
Sewer 1/23/2023 Approved BRIAN SULLIVAN
Underground Mechanical 2/6/2023 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Final 6/16/2023 Approved BRIAN SULLIVAN
PLUMBING-Final 6/16/2023 Approved BRIAN SULLIVAN
Gas Test 7/3/2023 Approved BRIAN SULLIVAN
HVAC-Final 7/3/2023 Corrections Issued BRIAN SULLIVAN
Final 7/19/2023 OK to Issue CofO BRIAN SULLIVAN
Green Building Final 7/19/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 7/19/2023 Approved BRIAN SULLIVAN
Smoke Detectors 7/19/2023 Approved BRIAN SULLIVAN