22032 W VALERIO ST 91303
Certificate Information: 22032 W VALERIO ST 91303
- Application / Permit
- 21010-10000-00564
- Plan Check / Job No.
- B21LA02049
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU
- Permit Issued
- Issued on 2/16/2022
- Issuing Office
- Current Status
- CofO Issued on 4/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | FERNANDO FLORES |
| Corrections Issued | 2/18/2021 | FERNANDO FLORES |
| Plan Check Approved | 10/28/2021 | FERNANDO FLORES |
| Building Plans Picked Up | 11/9/2021 | APPLICANT |
| Issued | 2/16/2022 | APPLICANT |
| CofO in Progress | 3/20/2023 | CHRIS CHRISTENSEN |
| CofO Issued | 4/5/2023 | JOHN JANSON |
| Permit Finaled | 4/5/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/8/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | ADRIAN CASTRO |
| Construction within easement | Cleared | 6/17/2021 | OSCAR CASTRO |
| Low Impact Development | Cleared | 9/24/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/27/2021 | ABDULLAH SADOZAI |
Contact Information
| Architect | , ; Lic. No.: C35683 | 10242 PARKINSON AVENUE WHITTIER, CA 90605 |
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/14/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/17/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/23/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 4/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 4/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/2/2022 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 5/2/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/31/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Gas Test | 5/31/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/31/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 5/31/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/31/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 5/31/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/31/2022 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 5/31/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/6/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/13/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 6/13/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 6/21/2022 | Conditional Approval | JESUS PINEDA |
| Drywall Nailing | 7/12/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 8/10/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/2/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 11/28/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 12/12/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 12/12/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/12/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 12/12/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 12/12/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Final | 12/12/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 12/12/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 12/12/2022 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 12/12/2022 | Partial Inspection | KRISTEN CAUSEY |
| Verify Sprinkler Sign Off | 12/12/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/12/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 1/12/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 1/12/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 1/12/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 1/12/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 1/12/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 2/9/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Final | 2/9/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/9/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 3/1/2023 | No Access for Inspection | KRISTEN CAUSEY |
| Service/Power Release | 3/1/2023 | No Access for Inspection | KRISTEN CAUSEY |
| Final | 3/14/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Service/Power Release | 3/14/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 3/17/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |