13738 W OXNARD ST 91401

Certificate Information: 13738 W OXNARD ST 91401

Application / Permit
21010-10000-00560
Plan Check / Job No.
B21LA02037
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (30'-2" X 39'-8") 1,172 SF 2 STORY ADU PER LAMC 12.22 A.33 (c)-(d). ** LID REQUIRED BEFORE C OF O OR FINAL OF PERMIT.
Permit Issued
Issued on 11/19/2021
Issuing Office
Current Status
CofO Issued on 11/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 VIVIAN LAO
Corrections Issued 3/4/2021 VIVIAN LAO
Quality Review Completed 3/5/2021 MICHAEL PEREZ
Applicant returned to address corrections 8/23/2021 VIVIAN LAO
Applicant returned to address corrections 10/26/2021 VIVIAN LAO
Plan Check Approved 11/1/2021 VIVIAN LAO
Plan Check Approved 11/1/2021 ANSINEE TOWNSEND
Issued 11/19/2021 APPLICANT
Building Plans Picked Up 12/1/2021 APPLICANT
CofO in Progress 11/8/2022 ARAM AVEDISIAN
Permit Finaled 11/17/2022 MICHAEL SMITH
CofO Issued 11/17/2022 MICHAEL SMITH
Permit Finaled 11/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/23/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/23/2021 GABRIEL ROBLES
Sewer availability Cleared 3/24/2021 GABRIEL ROBLES
"Q" conditions Cleared 3/31/2021 RICHARD REASER
Hydrant and Access approval Cleared 4/30/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 10/29/2021 DAGOVERTO GUERRERO
Public Works-Highway Ded. Cleared 10/27/2022 CHRISTINE REUSCH
Public Works-Open Permits Cleared 10/27/2022 CHRISTINE REUSCH
Public Works-Sewers Cleared 10/27/2022 CHRISTINE REUSCH

Contact Information

Contractor A J S Construction; Lic. No.: 695789-B 1045 RAYMOND AVENUE      GLENDALE, CA 91201

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2021 No Access for Inspection RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 1/25/2022 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 1/25/2022 Partial Approval RICHARD DOCKUS
Pre-Inspection 1/25/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 2/16/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/4/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 3/4/2022 Not Ready for Inspection RICHARD DOCKUS
Structural Steel Frame 3/4/2022 Partial Approval RICHARD DOCKUS
Underground Mechanical 3/4/2022 Partial Approval RICHARD DOCKUS
Verify Sprinkler Sign Off 3/4/2022 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 3/10/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/7/2022 Not Ready for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 4/7/2022 Corrections Issued RICHARD DOCKUS
Green Building Rough 4/7/2022 Not Ready for Inspection RICHARD DOCKUS
Verify Sprinkler Sign Off 4/7/2022 Not Ready for Inspection RICHARD DOCKUS
Deputy Wood Construction 4/8/2022 Conditional Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Partial Approval RICHARD DOCKUS
Wood Frame 4/12/2022 Partial Approval RICHARD DOCKUS
Deputy Wood Construction 5/6/2022 Conditional Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 6/8/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 6/16/2022 Approved RICHARD DOCKUS
HVAC-Rough 6/16/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/16/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 6/23/2022 Partial Approval RICHARD DOCKUS
Green Building Rough 6/23/2022 Approved RICHARD DOCKUS
Insulation 7/1/2022 Conditional Approval WILLIAM WREN
BUILDING-Rough-Frame 7/8/2022 Partial Approval RICHARD DOCKUS
Drywall Nailing 7/8/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Not Ready for Inspection RICHARD DOCKUS
Verify Sprinkler Sign Off 7/8/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Approved JENNIFER RABUCHIN
Wood Frame 7/14/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/19/2022 Approved RICHARD DOCKUS
Gas Test 7/27/2022 Approved CHRISTOPHE COCHRAN
Sewer 7/27/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 8/26/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 9/21/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 9/21/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 9/21/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 9/21/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 9/21/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 9/21/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 9/21/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 9/21/2022 Approved CHRISTOPHER DELLEFIELD
Structural Steel Frame 9/21/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 10/14/2022 Corrections Issued THOMAS FINNILA
HVAC-Final 10/14/2022 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 10/26/2022 Approved RICHARD DOCKUS
Final 10/26/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 10/26/2022 Approved RICHARD DOCKUS
HVAC-Final 10/26/2022 Approved RICHARD DOCKUS
PLUMBING-Final 10/26/2022 Approved RICHARD DOCKUS
Structural Steel Frame 10/26/2022 Approved RICHARD DOCKUS
Final 11/8/2022 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 11/8/2022 Approved ARAM AVEDISIAN