5731 N JUMILLA AVE 91367

Certificate Information: 5731 N JUMILLA AVE 91367

Application / Permit
21010-10000-00559
Plan Check / Job No.
B21LA02030
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 500 SF ADU at rear of lot, per GCS 65852.2 (e) (B) & LAMC 12.22 A.33 (c),(d),(g). NFPA 13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 11/22/2021
Issuing Office
Current Status
CofO Issued on 10/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2021 APPLICANT
Assigned to Plan Check Engineer 3/23/2021 AARON COSTA
Corrections Issued 3/23/2021 AARON COSTA
Applicant returned to address corrections 9/24/2021 GEORGE ALVAREZ
Plan Check Approved 11/4/2021 JOSEPH RAFOLS
Issued 11/22/2021 APPLICANT
Building Plans Picked Up 11/23/2021 APPLICANT
CofO in Progress 9/27/2023 JON MCHUGH
Permit Finaled 10/6/2023 JOHN JANSON
CofO Issued 10/6/2023 JOHN JANSON
Permit Finaled 10/6/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/12/2021 GABRIEL ROBLES
Sewer availability Cleared 5/19/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/24/2021 GABRIEL ROBLES
Low Impact Development Cleared 8/26/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 10/7/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/19/2021 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/18/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 3/18/2022 Approved SEAN HAUPT
PLUMBING-Rough 3/18/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 4/15/2022 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 4/15/2022 Approved SEAN HAUPT
Green Building Rough 4/15/2022 Not Ready for Inspection SEAN HAUPT
MERV13>=Rough 4/15/2022 Approved SEAN HAUPT
PLUMBING-Rough 4/15/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 4/15/2022 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Approved SEAN HAUPT
HVAC-Rough 4/19/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/4/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 5/4/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 5/4/2022 Approved SEAN HAUPT
Shower Pan 5/4/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 5/4/2022 Approved SEAN HAUPT
Insulation 5/16/2022 Approved MORRIS JACKSON
Drywall Nailing 5/24/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 5/24/2022 Approved SEAN HAUPT
ELECTRICAL-Final 10/31/2022 Approved SEAN HAUPT
Final 10/31/2022 Corrections Issued SEAN HAUPT
Green Building Final 10/31/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 10/31/2022 Approved SEAN HAUPT
MERV13>=Final 10/31/2022 Approved SEAN HAUPT
PLUMBING-Final 10/31/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 10/31/2022 Not Required SEAN HAUPT
Smoke Detectors 10/31/2022 Approved SEAN HAUPT
Final 9/26/2023 OK to Issue CofO JON MCHUGH
Green Building Final 9/26/2023 Approved JON MCHUGH