5731 N JUMILLA AVE 91367
Certificate Information: 5731 N JUMILLA AVE 91367
- Application / Permit
- 21010-10000-00559
- Plan Check / Job No.
- B21LA02030
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 500 SF ADU at rear of lot, per GCS 65852.2 (e) (B) & LAMC 12.22 A.33 (c),(d),(g). NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2021 | AARON COSTA |
| Corrections Issued | 3/23/2021 | AARON COSTA |
| Applicant returned to address corrections | 9/24/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 11/4/2021 | JOSEPH RAFOLS |
| Issued | 11/22/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| CofO in Progress | 9/27/2023 | JON MCHUGH |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
| CofO Issued | 10/6/2023 | JOHN JANSON |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/19/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 8/26/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 10/19/2021 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/18/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/18/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/15/2022 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 4/15/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 4/15/2022 | Not Ready for Inspection | SEAN HAUPT |
| MERV13>=Rough | 4/15/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 4/15/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 4/15/2022 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 4/19/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/4/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 5/4/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/4/2022 | Approved | SEAN HAUPT |
| Shower Pan | 5/4/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 5/4/2022 | Approved | SEAN HAUPT |
| Insulation | 5/16/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 5/24/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/24/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 10/31/2022 | Approved | SEAN HAUPT |
| Final | 10/31/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 10/31/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 10/31/2022 | Approved | SEAN HAUPT |
| MERV13>=Final | 10/31/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 10/31/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 10/31/2022 | Not Required | SEAN HAUPT |
| Smoke Detectors | 10/31/2022 | Approved | SEAN HAUPT |
| Final | 9/26/2023 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 9/26/2023 | Approved | JON MCHUGH |