2036 N STRADELLA ROAD 90077

Certificate Information: 2036 N STRADELLA ROAD 90077

Application / Permit
21010-10000-00558
Plan Check / Job No.
B21LA02025
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ELEVATED DECK
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 DANIEL YIP
Corrections Issued 2/26/2021 DANIEL YIP
Quality Review Completed 3/9/2021 JASON HEALEY
Building Plans Picked Up 3/18/2021 APPLICANT
Applicant returned to address corrections 4/28/2021 DANIEL YIP
Applicant returned to address corrections 5/21/2021 DANIEL YIP
Plan Check Approved 11/18/2021 DANIEL YIP
Issued 12/2/2021 APPLICANT
CofO in Progress 5/20/2025 CHRISTOPHER WILSON
Permit Finaled 5/27/2025 RICHARD STEINBACH
CofO Issued 5/27/2025 RICHARD STEINBACH
Permit Finaled 5/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/8/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/8/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/8/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/8/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/8/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/8/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/9/2021 DINAH GARIN
Sewer availability Cleared 3/9/2021 DINAH GARIN
ZI Cleared 3/9/2021 MIGUEL GAMBOA
Hydrant and Access approval Cleared 4/23/2021 MATTHEW CRAIG
Excavation more than 5-ft deep Cleared 4/30/2021 CALOSHA APPROVED
GPI Written Notices Cleared 4/30/2021 DANIEL YIP
Grading Pre-Inspection Cleared 4/30/2021 DANIEL YIP
Low Impact Development Cleared 7/2/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/28/2021 DINAH GARIN

Contact Information

Contractor Socal Home Builders Inc; Lic. No.: 1055386-B 13351 RIVERSIDE DRIVE #348      SHERMAN OAKS, CA 91423
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/30/2022 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 4/8/2022 Partial Approval CHRISTOPHER WILSON
Deputy Grading 4/15/2022 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/19/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/2/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/11/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/10/2022 Approved MICHAEL PELHAM
Deputy Reinf. Concrete 6/16/2022 Conditional Approval MICHAEL PELHAM
Deputy Grading 7/14/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Grading 7/15/2022 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 7/19/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 7/21/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/28/2022 Conditional Approval MICHAEL PELHAM
Deputy Grading 8/4/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/5/2022 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/8/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/9/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/7/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/8/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 10/3/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/5/2022 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 10/31/2022 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/31/2022 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 11/2/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/13/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/15/2022 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 12/23/2022 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/27/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/15/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/7/2023 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/7/2023 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 3/13/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 3/21/2023 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/29/2023 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 4/20/2023 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/20/2023 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/24/2023 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 4/25/2023 Conditional Approval MICHAEL PELHAM
Underground Mechanical 5/15/2023 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 5/18/2023 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/24/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 5/24/2023 Approved CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/26/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Partial Approval CHRISTOPHER WILSON
Green Building Rough 6/9/2023 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/9/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 6/12/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 7/3/2023 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Corrections Issued BRENDAN LOONEY
Green Building Rough 7/6/2023 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 7/6/2023 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 10/23/2023 Partial Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 11/2/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 11/20/2023 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 11/21/2023 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval CHRISTOPHER WILSON
Gas Test 11/27/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 11/27/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 12/22/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 1/5/2024 Approved CHRISTOPHER WILSON
HVAC-Rough 1/11/2024 Corrections Issued STEPHANIE SWANSON
Shower Pan 1/19/2024 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 1/29/2024 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/21/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 2/21/2024 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 2/21/2024 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 2/21/2024 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/22/2024 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/1/2024 Approved CHRISTOPHER WILSON
Green Building Rough 4/1/2024 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/1/2024 Approved CHRISTOPHER WILSON
Insulation 4/9/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 4/16/2024 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 4/18/2024 Approved CHRISTOPHER WILSON
Shower Pan 4/18/2024 Approved CHRISTOPHER WILSON
Drywall Nailing 4/30/2024 Approved MICHAEL PELHAM
HVAC-Final 12/20/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 1/14/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Final 1/17/2025 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 1/21/2025 Approved BOBBY KEY
ELECTRICAL-Final 1/30/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 2/6/2025 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 2/6/2025 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 2/18/2025 Approved CHRISTOPHER WILSON
Service/Power Release 2/18/2025 Approved CHRISTOPHER WILSON
Service/Power Release 3/19/2025 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Ready CHRISTOPHER WILSON
Final 5/19/2025 OK to Issue CofO CHRISTOPHER WILSON
Green Building Final 5/19/2025 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/19/2025 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 5/19/2025 Approved CHRISTOPHER WILSON