2935 S BRONSON AVE 90018
Certificate Information: 2935 S BRONSON AVE 90018
- Application / Permit
- 21010-10000-00529
- Plan Check / Job No.
- B21LA01897
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New detached ADU per ordinance 186,481.
- Permit Issued
- Issued on 12/24/2021
- Issuing Office
- Current Status
- CofO Issued on 10/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2021 | HELEN NGUYEN |
| Corrections Issued | 2/10/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/23/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/31/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 5/11/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/22/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/25/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 7/8/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/13/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/23/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/29/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/6/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/19/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/27/2021 | HELEN NGUYEN |
| Plan Check Approved | 12/16/2021 | PRANITA SHAH |
| Issued | 12/24/2021 | APPLICANT |
| CofO in Progress | 9/25/2024 | JUSTIN HAWLEY |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
| CofO Issued | 10/16/2024 | RUBEN SALAS |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 4/21/2021 | WALLIE JONG |
| Sewer availability | Cleared | 4/22/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 5/21/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 6/12/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/13/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 9/29/2021 | THOMAS LANG |
Contact Information
| Contractor | Stellar Construction Group; Lic. No.: 1014453-B | 119 NORTH FAIRFAX AVENUE # 224 LOS ANGELES, CA 90036 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/15/2022 | Corrections Issued | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/24/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/18/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/18/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 10/18/2022 | Approved | STUART CHAPMAN |
| Sewer | 10/18/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 10/18/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 10/18/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/22/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 11/30/2022 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 11/30/2022 | Partial Approval | CALEB MEISTER |
| Insulation | 12/22/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 1/24/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 1/24/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/24/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/24/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 2/28/2023 | Corrections Issued | CALEB MEISTER |
| Service/Power Release | 3/8/2023 | Approved | CALEB MEISTER |
| Final | 11/30/2023 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 11/30/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 11/30/2023 | Approved | RONNIE MINDANAO |
| Final | 12/5/2023 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/5/2023 | Approved | JUSTIN HAWLEY |
| Green Building Final | 12/5/2023 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 12/5/2023 | SGSOV Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 9/25/2024 | Approved | JUSTIN HAWLEY |
| Final | 9/25/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 9/25/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 9/25/2024 | Approved | JUSTIN HAWLEY |