4752 S MAIN ST 90037

Certificate Information: 4752 S MAIN ST 90037

Application / Permit
21010-10000-00520
Plan Check / Job No.
B21LA01854
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY 53 UNITS (52 LI = 100%) TYPE VA AFFORDABLE HOUSING APARMENT, TOC WITH BASE INCENTIVES ONLY
Permit Issued
Issued on 8/30/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 5/22/2023 MANUEL MONTUFAR
Issued 8/30/2023 APPLICANT
TCO Issued (Expire Date: 10-31-2026) 5/4/2026 ADAM BURGESS
CofO in Progress 5/19/2026 JAMES POWERS
Permit Finaled 5/19/2026 RAFAEL ESPINOZA
CofO Issued 5/19/2026 RAFAEL ESPINOZA
Permit Finaled 5/19/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 8/10/2022 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 8/11/2022 KEVIN ARUCAN
Community Plan Implem. Overlay Cleared 8/11/2022 STEVE MELGAR
Driveway location Cleared 8/11/2022 KEVIN ARUCAN
Historic Resource Verification Cleared 8/11/2022 MAX LODER
Trees in Parkway Cleared 8/15/2022 ADALBERTO VERA
Address approval Cleared 8/16/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/19/2022 STEVE MELGAR
Building over 36-ft Cleared 9/15/2022 CALOSHA APPROVED
Highway dedication Cleared 10/12/2022 JEANIE LAM
Sewer availability Cleared 11/2/2022 STEVE MELGAR
Hydrant and Access approval Cleared 11/9/2022 JOHN CONNEALLY
Low Impact Development Cleared 11/9/2022 JORGE MEJIA LEMUS
Green Code Cleared 11/10/2022 AARON COSTA
Permit Cleared 11/14/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 11/14/2022 STEVE MELGAR
Community Plan Implem. Overlay Cleared 12/21/2022 RIDWAN HARDY
Construction near power lines Cleared 12/21/2022 RIDWAN HARDY
Construction within easement Cleared 12/21/2022 RIDWAN HARDY
Fire Marshal Fire Life Safety Cleared 12/28/2022 ANDREW KO
Density Bonus 12.22.A.31 Cleared 1/3/2023 NICHOLAS KAWAZOE
Redevelopment Project Area Cleared 1/23/2023 GRACIELA ACOSTA
Community Plan Implem. Overlay Cleared 1/31/2023 MAYELA VILLA
Frnt yard landscape/Water mgmt Cleared 1/31/2023 MAYELA VILLA
Miscellaneous Cleared 1/31/2023 MAYELA VILLA
Opn space landscape/Water mgmt Cleared 1/31/2023 MAYELA VILLA
ZA Case Cleared 1/31/2023 MAYELA VILLA

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Foundational Builders Corp; Lic. No.: 1068191-B 9255 SUNSET BLVD STE 1100      WEST HOLLYWOOD, CA 90069
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Mcgrath,, Michael; Lic. No.: C86488 6092 KELSEY CIRCLE      HUNTINGTON BEACH, CA 92647

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/11/2023 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 9/13/2023 Partial Inspection LARRY ARNICK
Deputy Reinf. Concrete 12/13/2023 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 12/13/2023 Approved LARRY ARNICK
Reinforced Concrete Frame 12/13/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 12/14/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 12/18/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/5/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/5/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval LARRY ARNICK
Green Building Rough 2/13/2024 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 2/13/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 2/13/2024 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 3/1/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/12/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/12/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/18/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/22/2024 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 6/26/2024 Partial Approval JAMES POWERS
Wood Frame 6/27/2024 Partial Approval JAMES POWERS
Insulation 6/28/2024 Not Ready for Inspection JAMES POWERS
Insulation 7/1/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/2/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/3/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/3/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 7/10/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/12/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/16/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval JAMES POWERS
Insulation 7/30/2024 Partial Approval DANIEL VARNUM
Insulation 7/31/2024 Partial Approval DANIEL VARNUM
Insulation 8/2/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 8/5/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Partial Approval JAMES POWERS
Insulation 8/6/2024 Partial Approval JAMES POWERS
Insulation 8/7/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 8/16/2024 Partial Approval JAMES POWERS
Green Building Rough 8/16/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 8/16/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 8/16/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval JAMES POWERS
Insulation 8/26/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/9/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 9/9/2024 Partial Approval JAMES POWERS
Insulation 9/16/2024 Partial Approval JAMES POWERS
Wood Frame 9/24/2024 Partial Approval JAMES POWERS
Insulation 10/8/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/18/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/25/2024 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 10/31/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 10/31/2024 Partial Approval JAMES POWERS
Insulation 11/5/2024 Partial Approval JAMES POWERS
Insulation 11/15/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/4/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 12/4/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/9/2024 Partial Approval LARRY ARNICK
Insulation 12/16/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 12/16/2024 Partial Approval LARRY ARNICK
Wood Frame 12/23/2024 Partial Approval RONALD JIMENEZ
Insulation 1/2/2025 Partial Approval JAMES POWERS
Insulation 1/6/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/14/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/16/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/31/2025 Partial Approval JAMES POWERS
Wood Frame 2/12/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/18/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 2/19/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/26/2025 Approved JAMES POWERS
Light Gage Steel Frame 2/26/2025 Partial Approval JAMES POWERS
Insulation 2/28/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/28/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/12/2025 Partial Approval JAMES POWERS
Insulation 3/25/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/2/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/4/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/9/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 4/9/2025 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 8/26/2025 Partial Approval JAMES POWERS
Pre-Inspection 10/30/2025 Partial Approval JAMES POWERS
Final 4/8/2026 OK for TCO JAMES POWERS
Footing/Foundation/Slab 4/8/2026 Approved JAMES POWERS
Green Building Final 4/8/2026 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Approved JAMES POWERS
Smoke Detectors 4/8/2026 Approved JAMES POWERS
Verify Sprinkler Sign Off 4/8/2026 Approved JAMES POWERS
Wood Frame 4/8/2026 Approved JAMES POWERS
Final 4/21/2026 OK for TCO JAMES POWERS
Final 5/19/2026 OK to Issue CofO JAMES POWERS