Pre-Inspection
|
9/11/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Pre-Inspection
|
9/13/2023
|
Partial Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/13/2023
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
12/13/2023
|
Approved
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
12/13/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
12/14/2023
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
12/18/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/5/2024
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
1/5/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/13/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
2/13/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
2/13/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
2/13/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
3/1/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/1/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/15/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/8/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
4/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
4/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
4/18/2024
|
Partial Approval
|
JAMES POWERS
|
|
Masonry Wall/Backfill
|
4/22/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/7/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
6/26/2024
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
6/27/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
6/28/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
7/1/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/2/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/3/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
7/3/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/10/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/12/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/16/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/23/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/29/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/30/2024
|
Partial Approval
|
DANIEL VARNUM
|
|
Insulation
|
7/31/2024
|
Partial Approval
|
DANIEL VARNUM
|
|
Insulation
|
8/2/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/5/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/6/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/6/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/7/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
8/16/2024
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
8/16/2024
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
8/16/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
8/16/2024
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/26/2024
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/9/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
9/9/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
9/16/2024
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
9/24/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
10/8/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
10/18/2024
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
10/25/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/31/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
10/31/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
11/5/2024
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
11/15/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
12/4/2024
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
12/4/2024
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
12/9/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
12/16/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
12/16/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
12/23/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
1/2/2025
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
1/6/2025
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/14/2025
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
1/16/2025
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
1/31/2025
|
Partial Approval
|
JAMES POWERS
|
|
Wood Frame
|
2/12/2025
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
2/18/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
2/19/2025
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
2/26/2025
|
Approved
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
2/26/2025
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
2/28/2025
|
Partial Approval
|
JAMES POWERS
|
|
Light Gage Steel Frame
|
2/28/2025
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
3/12/2025
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
3/25/2025
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
4/2/2025
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
4/4/2025
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
4/9/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
4/9/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
8/26/2025
|
Partial Approval
|
JAMES POWERS
|
|
Pre-Inspection
|
10/30/2025
|
Partial Approval
|
JAMES POWERS
|
|
Final
|
4/8/2026
|
OK for TCO
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
4/8/2026
|
Approved
|
JAMES POWERS
|
|
Green Building Final
|
4/8/2026
|
Approved
|
JAMES POWERS
|
|
SGSOV-Seismic Gas S/O Valve
|
4/8/2026
|
SGSOV Approved
|
JAMES POWERS
|
|
Smoke Detectors
|
4/8/2026
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
4/8/2026
|
Approved
|
JAMES POWERS
|
|
Wood Frame
|
4/8/2026
|
Approved
|
JAMES POWERS
|
|
Final
|
4/21/2026
|
OK for TCO
|
JAMES POWERS
|
|
Final
|
5/19/2026
|
OK to Issue CofO
|
JAMES POWERS
|