7639 N RADFORD AVE 91605
Certificate Information: 7639 N RADFORD AVE 91605
- Application / Permit
- 21010-10000-00509
- Plan Check / Job No.
- B21LA01774
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. PROPOSED DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 2/26/2022
- Issuing Office
- Current Status
- CofO Issued on 7/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2021 | MICHAEL LOPEZ |
| Corrections Issued | 3/11/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 3/17/2021 | WING SUEN |
| Applicant returned to address corrections | 1/5/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 2/18/2022 | MICHAEL LOPEZ |
| Issued | 2/26/2022 | APPLICANT |
| CofO in Progress | 7/3/2023 | MATTHEW NELSON |
| Permit Finaled | 7/6/2023 | MICHAEL SMITH |
| CofO Issued | 7/6/2023 | MICHAEL SMITH |
| Permit Finaled | 7/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/12/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 5/20/2021 | JOHN CONNEALLY |
| ZI | Cleared | 6/11/2021 | STEVEN WECHSLER |
| Construction near power lines | Cleared | 7/2/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/2/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/31/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 2/7/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/11/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/11/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 6/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 6/16/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/25/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 7/25/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/1/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 8/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/18/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/31/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 10/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 10/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 12/2/2022 | Corrections Issued | MATTHEW NELSON |
| Final | 6/14/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 6/14/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 6/14/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 6/14/2023 | Approved | MATTHEW NELSON |
| Final | 6/30/2023 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 6/30/2023 | Approved | MATTHEW NELSON |