8423 S BLERIOT AVE 90045
Certificate Information: 8423 S BLERIOT AVE 90045
- Application / Permit
- 21010-10000-00507
- Plan Check / Job No.
- B21LA01772
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU. (2-STORY) PER ORDINANCE
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | CARLOS MONTES |
| Corrections Issued | 2/23/2021 | CARLOS MONTES |
| Quality Review Completed | 3/5/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/15/2021 | CARLOS MONTES |
| Plan Check Approved | 10/7/2021 | CARLOS MONTES |
| Issued | 10/12/2021 | APPLICANT |
| CofO in Progress | 4/17/2023 | BOBBY KEY |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
| CofO Issued | 4/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/24/2021 | RIDWAN HARDY |
| Address approval | Cleared | 4/26/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 4/26/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2021 | DENNIS BRAGIN |
| Specific Plan | Cleared | 5/25/2021 | PETE EYRE |
| Hydrant and Access approval | Cleared | 5/28/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/21/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | DENNIS BRAGIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
| Engineer | Smith,, David Michael; Lic. No.: C37222 | 16611 LANDMARK AVE YORBA LINDA, CA 92886 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/9/2022 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 3/9/2022 | Partial Inspection | RICHARD STEINBACH |
| Special/Order Compliance | 3/9/2022 | Corrections Issued | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 3/14/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 4/7/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 5/13/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 5/13/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 6/3/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 6/9/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/28/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/28/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Special/Order Compliance | 7/1/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2022 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 7/12/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 8/2/2022 | Approved | BOBBY KEY |
| Green Building Rough | 8/2/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/2/2022 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 8/2/2022 | Approved | BOBBY KEY |
| Insulation | 8/9/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 8/23/2022 | Approved | BOBBY KEY |
| Final | 8/23/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 9/7/2022 | Partial Approval | BOBBY KEY |
| Shower Pan | 9/7/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 9/8/2022 | Approved | BOBBY KEY |
| Shower Pan | 9/8/2022 | Approved | BOBBY KEY |
| Sewer | 11/30/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/6/2023 | Corrections Issued | BOBBY KEY |
| Final | 3/6/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 3/6/2023 | Approved | BOBBY KEY |
| HVAC-Final | 3/6/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 3/6/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 3/6/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/17/2023 | Approved | BOBBY KEY |
| Final | 4/17/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 4/17/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 4/17/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 4/17/2023 | Approved | BOBBY KEY |