14636 W NURMI ST 91342

Certificate Information: 14636 W NURMI ST 91342

Application / Permit
21010-10000-00504
Plan Check / Job No.
B21LA01769
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU (1-STORY) PER ORDINANCE
Permit Issued
Issued on 12/22/2021
Issuing Office
Current Status
CofO Issued on 9/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 CARLOS MONTES
Corrections Issued 2/19/2021 CARLOS MONTES
Quality Review Completed 2/26/2021 HERNAN ARREOLA
Applicant returned to address corrections 4/29/2021 CARLOS MONTES
Applicant returned to address corrections 5/11/2021 CARLOS MONTES
Applicant returned to address corrections 6/22/2021 CARLOS MONTES
Applicant returned to address corrections 11/2/2021 CARLOS MONTES
Plan Check Approved 12/17/2021 CARLOS MONTES
Issued 12/22/2021 APPLICANT
CofO in Progress 9/6/2022 ARAM AVEDISIAN
CofO Issued 9/13/2022 MICHAEL SMITH
Permit Finaled 9/13/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/17/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/17/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/17/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 9/7/2021 ROBERT DUFF
Low Impact Development Cleared 10/22/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 10/28/2021 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/28/2021 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/6/2022 Approved JOHN HAYES
Underground Mechanical 1/6/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 4/29/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 4/29/2022 Not Ready for Inspection JOHN HAYES
HVAC-Rough 4/29/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/29/2022 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 5/9/2022 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 5/17/2022 Approved JOHN HAYES
ELECTRICAL-Rough 5/17/2022 Approved JOHN HAYES
Green Building Rough 5/17/2022 Approved JOHN HAYES
HVAC-Rough 5/17/2022 Approved JOHN HAYES
PLUMBING-Rough 5/17/2022 Approved JOHN HAYES
Verify Sprinkler Sign Off 5/17/2022 Approved JOHN HAYES
Insulation 5/20/2022 Approved JOHN HAYES
Special/Order Compliance 5/20/2022 Approved JOHN HAYES
Drywall Nailing 5/23/2022 Approved JOHN HAYES
Interior/Exterior Lathing 6/7/2022 Approved JOHN HAYES
Underground Mechanical 6/7/2022 Approved JOHN HAYES
Final 8/24/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 8/24/2022 Approved ARAM AVEDISIAN
Green Building Final 8/24/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 8/24/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 9/6/2022 Approved ARAM AVEDISIAN
Final 9/6/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 9/6/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 9/6/2022 Approved ARAM AVEDISIAN
Service/Power Release 9/6/2022 Approved ARAM AVEDISIAN