6219 N GLIDE AVE 91367

Certificate Information: 6219 N GLIDE AVE 91367

Application / Permit
21010-10000-00500
Plan Check / Job No.
B21LA01724
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (20.5' X 38'-5") 1 STORY ADU PER LAMC 12.22 A.33(c)-(d). ** LID REQ BEFORE C OF O AND/OR FINAL OF PERMIT.
Permit Issued
Issued on 9/24/2021
Issuing Office
Current Status
Issued on 9/24/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 VIVIAN LAO
Corrections Issued 2/18/2021 VIVIAN LAO
Quality Review Completed 2/23/2021 MICHAEL PEREZ
Building Plans Picked Up 3/2/2021 APPLICANT
Applicant returned to address corrections 4/29/2021 VIVIAN LAO
Applicant returned to address corrections 7/26/2021 VIVIAN LAO
Applicant returned to address corrections 8/11/2021 VIVIAN LAO
Applicant returned to address corrections 9/10/2021 VIVIAN LAO
Plan Check Approved 9/24/2021 VIVIAN LAO
Issued 9/24/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/7/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/2/2021 GABRIEL ROBLES
Sewer availability Cleared 6/2/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 7/23/2021 JOHN CONNEALLY
Construction near power lines Cleared 8/6/2021 RIDWAN HARDY
Construction within easement Cleared 8/6/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 9/22/2021 GABRIEL ROBLES

Contact Information

Contractor La-Decks; Lic. No.: 968237-B 10880 WILSHSIRE BLVD 1101      LOS ANGELES, CA 90024

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 6/9/2022 Approved TROY SANDERS
Drywall Nailing 6/9/2022 Approved TROY SANDERS
Final 6/9/2022 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 6/9/2022 Approved TROY SANDERS
Green Building Final 6/9/2022 Approved TROY SANDERS
Green Building Rough 6/9/2022 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 6/9/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Approved TROY SANDERS
Service/Power Release 6/9/2022 Approved TROY SANDERS
Smoke Detectors 6/9/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 6/9/2022 Approved TROY SANDERS