11991-11993 W BRAY ST 90230
Certificate Information: 11991-11993 W BRAY ST 90230
- Application / Permit
- 21010-10000-00494
- Plan Check / Job No.
- B21LA01684
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-story duplex with attached 8-car carport. Fire sprinkler is provided throughout the building. Building B.
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- CofO Issued on 7/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | HELEN NGUYEN |
| Corrections Issued | 2/9/2021 | HELEN NGUYEN |
| Quality Review Completed | 2/16/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 2/18/2021 | APPLICANT |
| Applicant returned to address corrections | 7/31/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/3/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/16/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/20/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/23/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/29/2021 | HELEN NGUYEN |
| Plan Check Approved | 11/16/2021 | HELEN NGUYEN |
| Issued | 11/16/2021 | APPLICANT |
| CofO in Progress | 7/19/2023 | HERBERT GIRON |
| Permit Finaled | 7/19/2023 | DANIEL ORRANTE |
| CofO Issued | 7/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/19/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2021 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 3/11/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 3/11/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 4/26/2021 | KURT CORRAL |
| Specific Plan | Cleared | 5/19/2021 | FREDDY GARCIA |
| Highway dedication | Cleared | 5/20/2021 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 8/12/2021 | YVAINNE GALSIM |
| Permit | Cleared | 8/13/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 8/13/2021 | DINAH GARIN |
Contact Information
| Architect | Schneider,, Matthew P; Lic. No.: C31660 | 2110 ARTESIA BLVD STE B430 REDONDO BEACH, CA 90278 |
| Contractor | Jeff Mac Construction; Lic. No.: 622633-B | 23717 S HAWTHORNE BLVD # 101 TORRANCE, CA 90505 |
| Engineer | Arriola,, Kirby Norman; Lic. No.: C31416 | PO BOX 5566 OXNARD, CA 93031 |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
| Engineer | Tucker,, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
| Landscape Architect | George,, Gregory William; Lic. No.: LA6230 | 2608 CORAL RIDGE RD RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/12/2022 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Barrier | 1/12/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 1/12/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/10/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/16/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 3/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Sewer | 3/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/17/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/23/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 4/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| MERV13>=Rough | 4/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| METHANE-Rough | 4/27/2022 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | PATRICK QUALEY |
| BUILDING-Rough-Frame | 8/23/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | HERBERT GIRON |
| MERV13>=Rough | 8/23/2022 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/23/2022 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Wood Construction | 8/25/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/15/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 9/15/2022 | Not Ready for Inspection | HERBERT GIRON |
| MERV13>=Rough | 9/15/2022 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 9/15/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 9/26/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 10/4/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 10/7/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 10/14/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 10/14/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 10/19/2022 | Not Ready for Inspection | HERBERT GIRON |
| MERV13>=Rough | 10/19/2022 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 10/19/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 10/24/2022 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 10/24/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/1/2022 | Partial Approval | HERBERT GIRON |
| Insulation | 11/1/2022 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 11/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 11/4/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/7/2022 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 11/7/2022 | Not Ready for Inspection | HERBERT GIRON |
| Light Gage Steel Frame | 11/7/2022 | Conditional Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 11/9/2022 | Partial Approval | HERBERT GIRON |
| Light Gage Steel Frame | 11/9/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/10/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 11/10/2022 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 11/10/2022 | Approved | HERBERT GIRON |
| Insulation | 11/16/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 11/30/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 12/28/2022 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 12/28/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 2/24/2023 | Approved | HERBERT GIRON |
| Gas Test | 2/24/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 2/24/2023 | Approved | HERBERT GIRON |
| Gas Test | 3/6/2023 | Approved | HERBERT GIRON |
| Underground Mechanical | 3/13/2023 | Approved | HERBERT GIRON |
| Deputy Drilled-In Anchors | 4/10/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Final | 5/3/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 5/4/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 5/4/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 5/11/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 5/12/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 5/22/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 6/2/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 6/2/2023 | Approved | HERBERT GIRON |
| Green Building Final | 6/9/2023 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 7/10/2023 | Approved | HERBERT GIRON |
| Final | 7/10/2023 | Corrections Issued | HERBERT GIRON |
| MERV13>=Final | 7/10/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 7/10/2023 | Approved | HERBERT GIRON |
| Final | 7/13/2023 | Corrections Issued | HERBERT GIRON |
| Final | 7/18/2023 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 7/18/2023 | Approved | HERBERT GIRON |