6648 W 81ST ST 90045

Certificate Information: 6648 W 81ST ST 90045

Application / Permit
21010-10000-00478
Plan Check / Job No.
B21LA01626
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION 2-STORY ADU W/ ROOF DECK TO (E) 2-CAR GARAGE PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/5/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 KHEDER ALRAZAA
Corrections Issued 2/8/2021 KHEDER ALRAZAA
Quality Review Completed 2/10/2021 JASON HEALEY
Building Plans Picked Up 2/18/2021 APPLICANT
Applicant returned to address corrections 7/2/2021 KHEDER ALRAZAA
Plan Check Approved 8/16/2022 KHEDER ALRAZAA
Issued 3/5/2024 APPLICANT
CofO in Progress 5/13/2025 JESUS PINEDA
Permit Finaled 5/16/2025 RICHARD STEINBACH
CofO Issued 5/16/2025 RICHARD STEINBACH
Permit Finaled 5/16/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 7/15/2021 KEVIN ARUCAN
Hydrant and Access approval Cleared 9/11/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/3/2022 SUNG JOON WON
Address approval Cleared 7/28/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/29/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 7/29/2022 DINAH GARIN
Sewer availability Cleared 7/29/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770
Engineer Wong,, George Voon; Lic. No.: C49894 516 N MOORE AVE E      MONTEREY PARK, CA 91754

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/21/2024 Partial Approval BOBBY KEY
Sewer 6/21/2024 Approved BOBBY KEY
Footing/Foundation/Slab 6/26/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Corrections Issued BOBBY KEY
Deputy Wood Construction 7/18/2024 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Approval TEMISTOCLES CAAL
Sewer 7/22/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 9/17/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Corrections Issued BOBBY KEY
Deputy Wood Construction 9/18/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 9/20/2024 Corrections Issued DAVID FEILER
Green Building Rough 9/20/2024 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 9/30/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 9/30/2024 Corrections Issued BOBBY KEY
Green Building Rough 9/30/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 9/30/2024 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 9/30/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 9/30/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 10/7/2024 Not Ready for Inspection BOBBY KEY
Green Building Rough 10/7/2024 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 10/7/2024 Not Ready for Inspection BOBBY KEY
Rough-Elec/Plmb/HVAC 10/7/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 10/28/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Approved TEMISTOCLES CAAL
Green Building Rough 10/28/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 10/28/2024 Partial Approval TEMISTOCLES CAAL
Insulation 11/12/2024 Approved TEMISTOCLES CAAL
Shower Pan 11/12/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 11/18/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 11/18/2024 Approved MICHAEL ALLEN
ELECTRICAL-Final 3/17/2025 Approved JESUS PINEDA
Final 3/17/2025 Corrections Issued JESUS PINEDA
Green Building Final 3/17/2025 Corrections Issued JESUS PINEDA
HVAC-Final 3/17/2025 Approved JESUS PINEDA
PLUMBING-Final 3/17/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Not Required JESUS PINEDA
Smoke Detectors 3/17/2025 Approved JESUS PINEDA
Final 3/19/2025 Not Ready for Inspection JESUS PINEDA
Green Building Final 3/19/2025 Approved JESUS PINEDA
Final 5/13/2025 OK to Issue CofO JESUS PINEDA
Service/Power Release 5/13/2025 Approved JESUS PINEDA