Permit Issued
Issued on 11/1/2023
Issuing Office
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 CARLOS MONTES
Corrections Issued 2/20/2021 CARLOS MONTES
Quality Review Completed 3/5/2021 HERNAN ARREOLA
Applicant returned to address corrections 11/3/2021 CARLOS MONTES
Applicant returned to address corrections 12/8/2021 CARLOS MONTES
Applicant returned to address corrections 1/6/2022 CARLOS MONTES
Applicant returned to address corrections 1/24/2023 CARLOS MONTES
Plan Check Approved 8/4/2023 CARLOS MONTES
Issued 11/1/2023 APPLICANT
CofO in Progress 11/22/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 1/27/2026 RUBEN SALAS
CofO Issued 1/27/2026 RUBEN SALAS
Permit Finaled 1/27/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/7/2021 CARLOS AGUILERA
Permit Cleared 6/7/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/8/2021 CARLOS AGUILERA
Sewer availability Cleared 6/8/2021 CARLOS AGUILERA
Construction within easement Cleared 8/24/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 9/18/2021 RUEL COLE
Low Impact Development Cleared 1/3/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 1/4/2023 LEE GUILBEAUX

Contact Information

Architect Resendiz,, Alejandro; Lic. No.: C11660 PHILLIPS RANCH   52 CARRIAGE WAY    POMONA, CA 91766
Contractor Owner-Builder       ,
Engineer Solis,, Ralph Joseph; Lic. No.: C35480 1611 LAUREL AVE      REDLANDS, CA 92373

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/4/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 12/7/2023 Partial Approval JOHN HAYES
Footing/Foundation/Slab 12/12/2023 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 12/27/2023 Corrections Issued JOHN HAYES
Green Building Rough 12/27/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/27/2023 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 12/27/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 12/29/2023 Approved CRAIG DAVIS
BUILDING-Rough-Frame 1/16/2024 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 2/20/2024 Not Ready for Inspection CRAIG DAVIS
Green Building Rough 2/20/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 2/20/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 2/20/2024 Corrections Issued CRAIG DAVIS
Verify Sprinkler Sign Off 2/20/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 2/26/2024 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 2/26/2024 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/12/2024 Partial Approval THOMAS FINNILA
Green Building Rough 3/12/2024 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 3/12/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 3/19/2024 Partial Inspection JOHN COLEMAN
ELECTRICAL-Rough 3/19/2024 Approved JOHN COLEMAN
Green Building Rough 3/19/2024 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 3/19/2024 Approved JOHN COLEMAN
PLUMBING-Rough 3/19/2024 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 3/19/2024 Approved JOHN COLEMAN
Insulation 3/22/2024 Corrections Issued JOHN HAYES
Insulation 3/28/2024 Approved JOHN COLEMAN
Drywall Nailing 4/2/2024 Approved RYAN SALAZAR
Green Building Rough 4/2/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/30/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 5/30/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 5/30/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 5/30/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 5/30/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/30/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Sewer 5/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/30/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/4/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/4/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 6/12/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 8/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 8/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 8/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 8/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 8/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 8/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 8/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/4/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 9/4/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 9/4/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/4/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/4/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 9/11/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 9/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 9/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 9/11/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 9/11/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/11/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/11/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Final 12/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 12/26/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 12/26/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 12/26/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Final 5/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/12/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 11/21/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 11/21/2025 Approved ROBERTO PALACIOS-LOPEZ