11165 N HERRICK AVE 91331
Certificate Information: 11165 N HERRICK AVE 91331
- Application / Permit
- 21010-10000-00456
- Plan Check / Job No.
- B21LA01498
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Proposed new 1,200 square foot ADU toward the rear of the property.
- Permit Issued
- Issued on 12/30/2021
- Issuing Office
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | JOE VO |
| Corrections Issued | 2/6/2021 | JOE VO |
| Quality Review Completed | 2/21/2021 | HERNAN ARREOLA |
| Plan Check Approved | 12/27/2021 | JOE VO |
| Issued | 12/30/2021 | APPLICANT |
| CofO in Progress | 6/2/2022 | MICHEL ABAJAN |
| Permit Finaled | 6/15/2022 | MICHAEL SMITH |
| CofO Issued | 6/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/9/2021 | LEE GUILBEAUX |
| Clean Up Green Up | Cleared | 9/23/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 10/5/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/6/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 12/14/2021 | GREGORY HOERNER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/11/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/11/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/18/2022 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 1/18/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/10/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/10/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/10/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/10/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 2/10/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/10/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/10/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/18/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 2/18/2022 | Partial Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/18/2022 | Approved | MICHEL ABAJAN |
| Insulation | 3/2/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/2/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/7/2022 | Partial Approval | MICHEL ABAJAN |
| Drywall Nailing | 3/8/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/23/2022 | Approved | MICHEL ABAJAN |
| Service/Power Release | 3/23/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/2/2022 | Approved | MICHEL ABAJAN |
| Final | 6/2/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 6/2/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/2/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/2/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 6/2/2022 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 6/2/2022 | Approved | MICHEL ABAJAN |