926 N MCDONALD AVE 90744
Certificate Information: 926 N MCDONALD AVE 90744
- Application / Permit
- 21010-10000-00455
- Plan Check / Job No.
- B21LA01497
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU at rear of lot.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- Issued on 5/20/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2021 | JOE VO |
| Corrections Issued | 1/30/2021 | JOE VO |
| Applicant returned to address corrections | 4/16/2021 | JOE VO |
| Applicant returned to address corrections | 5/7/2021 | JOE VO |
| Plan Check Approved | 5/13/2021 | JOE VO |
| Issued | 5/20/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2021 | ERIK BEASLEY |
| Highway dedication | Cleared | 3/17/2021 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/17/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/17/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 4/9/2021 | KURT CORRAL |
| "Q" conditions | Cleared | 4/13/2021 | RICHARD REASER |
| Clean Up Green Up | Cleared | 4/13/2021 | RICHARD REASER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/10/2022 | Conditional Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 2/14/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/22/2022 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Rough | 2/22/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/25/2022 | Approved | ANSON MAGLASANG |
| METHANE-Barrier | 2/25/2022 | Approved | ANSON MAGLASANG |
| METHANE-Subgrade | 2/25/2022 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/14/2022 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/14/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 3/14/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 3/14/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 3/14/2022 | Corrections Issued | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 3/14/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/16/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 3/16/2022 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 3/16/2022 | Approved | EUGENE CASSIDY |
| Insulation | 3/24/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/24/2022 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 3/30/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/30/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/7/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 4/7/2022 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/11/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 4/11/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/24/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/24/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/24/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 5/24/2022 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Rough | 5/24/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 5/24/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 5/24/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/23/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/23/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/23/2022 | Approved | EUGENE CASSIDY |
| METHANE-Final | 6/23/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 6/23/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/23/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 6/23/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/14/2022 | Approved | EUGENE CASSIDY |
| Final | 7/14/2022 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Final | 7/14/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 7/14/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 7/14/2022 | Not Ready for Inspection | EUGENE CASSIDY |