7019 1/2 S BONSALLO AVE 90044

Certificate Information: 7019 1/2 S BONSALLO AVE 90044

Application / Permit
21010-10000-00452
Plan Check / Job No.
B21LA01488
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 9/20/2021
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 CRYSTEL MAALOUF
Corrections Issued 2/8/2021 CRYSTEL MAALOUF
Quality Review Completed 2/23/2021 WING SUEN
Applicant returned to address corrections 7/8/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 7/23/2021 CRYSTEL MAALOUF
Plan Check Approved 9/1/2021 CRYSTEL MAALOUF
Issued 9/20/2021 APPLICANT
CofO in Progress 3/23/2023 LILIANA PORTILLO
Permit Finaled 4/8/2023 DEROLD HAUFF
CofO Issued 4/8/2023 DEROLD HAUFF
Permit Finaled 4/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/1/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/5/2021 CELINA MORENO
Sewer availability Cleared 4/5/2021 CELINA MORENO
Construction near power lines Cleared 5/13/2021 RIDWAN HARDY
Construction within easement Cleared 5/13/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 5/22/2021 ROBERT DUFF
Low Impact Development Cleared 6/16/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/16/2021 CELINA MORENO

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3627 E FIRST STREET      LOS ANGELES, CA 90063
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 11/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 11/19/2021 Approved JOAQUIN GREENOUGH
Underground Mechanical 11/19/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/14/2022 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/14/2022 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Partial Inspection FREDDIE RIVERA
HVAC-Rough 1/14/2022 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 1/14/2022 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 1/14/2022 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/21/2022 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Conditional Approval LILIANA PORTILLO
Green Building Rough 1/21/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 1/21/2022 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 1/21/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 2/25/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 2/25/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 3/3/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 3/3/2022 Approved LILIANA PORTILLO
HVAC-Rough 3/3/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/3/2022 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 3/10/2022 Corrections Issued LILIANA PORTILLO
Insulation 3/10/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 3/22/2022 Approved LILIANA PORTILLO
Drywall Nailing 3/22/2022 Corrections Issued LILIANA PORTILLO
Green Building Rough 3/22/2022 Approved LILIANA PORTILLO
Insulation 3/22/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 3/22/2022 Approved LILIANA PORTILLO
Drywall Nailing 3/31/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/31/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/9/2022 Corrections Issued LILIANA PORTILLO
Final 6/9/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 6/9/2022 Approved LILIANA PORTILLO
Green Building Final 6/9/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 6/9/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 6/9/2022 Approved LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 7/5/2022 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Final 7/15/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 7/15/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 7/15/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/15/2022 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 7/15/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 7/29/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 7/29/2022 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 7/29/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 7/29/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 8/12/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 8/12/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 8/12/2022 Conditional Approval LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/12/2022 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 8/12/2022 Not Ready for Inspection LILIANA PORTILLO
Pre-Inspection 8/17/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 9/20/2022 Conditional Approval LILIANA PORTILLO
Final 9/20/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 9/20/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 9/20/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 9/20/2022 Not Ready for Inspection LILIANA PORTILLO
Final 10/26/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 10/26/2022 Approved LILIANA PORTILLO
Service/Power Release 10/26/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 12/20/2022 Approved LILIANA PORTILLO
Final 12/20/2022 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 12/20/2022 Not Ready for Inspection LILIANA PORTILLO
Final 3/22/2023 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 3/22/2023 Approved LILIANA PORTILLO