3746 W VALLEYBRINK ROAD 90039
Certificate Information: 3746 W VALLEYBRINK ROAD 90039
- Application / Permit
- 21010-10000-00449
- Plan Check / Job No.
- B21LA01450
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU PER LAMC 12.22 A33 C&D, SEE COMMENTS
- Permit Issued
- Issued on 12/30/2021
- Issuing Office
- Current Status
- CofO Issued on 8/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | STARR CHEN |
| Corrections Issued | 3/8/2021 | STARR CHEN |
| Quality Review Completed | 3/9/2021 | JASON HEALEY |
| Building Plans Picked Up | 4/1/2021 | APPLICANT |
| Applicant returned to address corrections | 5/27/2021 | STARR CHEN |
| Applicant returned to address corrections | 8/5/2021 | STARR CHEN |
| Applicant returned to address corrections | 9/9/2021 | STARR CHEN |
| Applicant returned to address corrections | 12/9/2021 | STARR CHEN |
| Plan Check Approved | 12/30/2021 | STARR CHEN |
| Issued | 12/30/2021 | APPLICANT |
| CofO in Progress | 8/22/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/24/2023 | RONALD MYRICK |
| CofO Issued | 8/24/2023 | RONALD MYRICK |
| Permit Finaled | 8/24/2023 | RONALD MYRICK |
Permit Application Clearance Information
| ZI | Cleared | 6/8/2021 | RICHARD REASER |
| Address approval | Cleared | 6/16/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/26/2021 | WALLIE JONG |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/8/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 11/19/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 11/19/2021 | WALLIE JONG |
Contact Information
| Contractor | Ras-A Build Llc; Lic. No.: 1014457-B | 2507 190TH STREET REDONDO BEACH, CA 90278 |
| Engineer | Mccullum,, Eric William; Lic. No.: C68850 | 727 2ND ST STE 104 HERMOSA BEACH, CA 90254 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/7/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/9/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 3/9/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/15/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/15/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/30/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 8/3/2022 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/7/2022 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 9/9/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 10/4/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 10/4/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 10/4/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/4/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/11/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/11/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/14/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 10/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/14/2022 | Partial Approval | HAMIK HARTOUNIAN |
| MERV13>=Rough | 10/14/2022 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/28/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 10/28/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 10/28/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/28/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/2/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/2/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/2/2022 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 11/2/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/7/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/7/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/10/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/30/2022 | Approved | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 4/21/2023 | Approved | SCOTT FINNILA |
| Underground Mechanical | 4/21/2023 | Partial Approval | SCOTT FINNILA |
| HVAC-Final | 5/15/2023 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Final | 5/15/2023 | Partial Inspection | SCOTT FINNILA |
| Pre-Inspection | 6/2/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/2/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/9/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 7/7/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 7/7/2023 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 7/7/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/7/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 7/25/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 7/25/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 8/7/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 8/7/2023 | Not Required | HAMIK HARTOUNIAN |
| Final | 8/18/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |