1331-1333 E 49TH ST 90011
Certificate Information: 1331-1333 E 49TH ST 90011
- Application / Permit
- 21010-10000-00442
- Plan Check / Job No.
- B21LA01423
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 6/8/2021
- Issuing Office
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | DANIEL YIP |
| Corrections Issued | 2/17/2021 | DANIEL YIP |
| Quality Review Completed | 2/18/2021 | JASON HEALEY |
| Building Plans Picked Up | 2/23/2021 | APPLICANT |
| Plan Check Approved | 5/20/2021 | DANIEL YIP |
| Issued | 6/8/2021 | APPLICANT |
| CofO in Progress | 12/23/2021 | JOAQUIN GREENOUGH |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
| CofO Issued | 1/8/2022 | DEROLD HAUFF |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 3/5/2021 | ROBERT DUFF |
| Sewer availability | Cleared | 3/8/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 4/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/3/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2021 | Approved | JOAQUIN GREENOUGH |
| Special/Order Compliance | 6/28/2021 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 7/20/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 7/20/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2021 | Partial Approval | ELMER BLAND |
| Insulation | 7/21/2021 | Partial Approval | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 9/9/2021 | Conditional Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/24/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/24/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 9/24/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/24/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/24/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 9/24/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 9/24/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 9/27/2021 | Corrections Issued | CALEB MEISTER |
| HVAC-Rough | 9/27/2021 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 9/27/2021 | Approved | CALEB MEISTER |
| Pre-Inspection | 9/27/2021 | Partial Inspection | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/28/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 9/28/2021 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 9/28/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/30/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 10/5/2021 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 10/20/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/20/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| Drywall Nailing | 10/25/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 10/25/2021 | Approved | AMY COLIN |
| ELECTRICAL-Final | 12/1/2021 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 12/21/2021 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Green Building Final | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 12/21/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 12/23/2021 | Approved | JOAQUIN GREENOUGH |