1311-1313 W 53RD ST 90037
Certificate Information: 1311-1313 W 53RD ST 90037
- Application / Permit
- 21010-10000-00385
- Plan Check / Job No.
- B21LA01255
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
- Permit Issued
- Issued on 12/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | DANIEL YIP |
| Corrections Issued | 2/17/2021 | DANIEL YIP |
| Quality Review Completed | 2/18/2021 | JASON HEALEY |
| Building Plans Picked Up | 2/23/2021 | APPLICANT |
| Plan Check Approved | 9/15/2022 | DANIEL YIP |
| Issued | 12/29/2022 | APPLICANT |
| CofO in Progress | 5/21/2023 | SABAS ALONSO |
| Permit Finaled | 6/15/2023 | DEROLD HAUFF |
| CofO Issued | 6/15/2023 | DEROLD HAUFF |
| Permit Finaled | 6/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | CECILIO NAVARRO |
| Trees in Parkway | Cleared | 4/8/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 4/23/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/26/2022 | JORGE MEJIA LEMUS |
| Permit | Cleared | 9/3/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 9/3/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/6/2022 | JEANETTE VONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/18/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 1/19/2023 | Conditional Approval | SABAS ALONSO |
| PLUMBING-Rough | 1/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 1/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 1/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/30/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 1/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 1/31/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 2/21/2023 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/10/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/10/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/10/2023 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 3/10/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/16/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 3/21/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 3/21/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/1/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/19/2023 | Approved | SABAS ALONSO |
| Final | 5/19/2023 | OK to Issue CofO | SABAS ALONSO |
| Footing/Foundation/Slab | 5/19/2023 | Approved | SABAS ALONSO |
| Gas Test | 5/19/2023 | Approved | SABAS ALONSO |
| Green Building Final | 5/19/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 5/19/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 5/19/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 5/19/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 5/19/2023 | Approved | SABAS ALONSO |