204-206 E 53RD ST 90011
Certificate Information: 204-206 E 53RD ST 90011
- Application / Permit
- 21010-10000-00378
- Plan Check / Job No.
- B21LA01210
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE IN THE FRONT AND 2-CAR GARAGE IN THE REAR.
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | DANIEL YIP |
| Corrections Issued | 2/17/2021 | DANIEL YIP |
| Quality Review Completed | 2/18/2021 | JASON HEALEY |
| Building Plans Picked Up | 2/23/2021 | APPLICANT |
| Plan Check Approved | 9/2/2021 | DANIEL YIP |
| Issued | 9/22/2021 | APPLICANT |
| CofO in Progress | 4/29/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | CECILIO NAVARRO |
| Trees in Parkway | Cleared | 4/8/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 4/23/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 7/21/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 8/13/2021 | YVAINNE GALSIM |
| Permit | Cleared | 8/17/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/17/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| Special/Order Compliance | 11/15/2021 | Partial Inspection | ADAM ESCOTO |
| Special/Order Compliance | 11/15/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 11/15/2021 | Partial Inspection | AMY COLIN |
| Special/Order Compliance | 11/15/2021 | Partial Inspection | JUSTIN HAWLEY |
| Special/Order Compliance | 11/15/2021 | Partial Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 11/29/2021 | Approved | SABAS ALONSO |
| Insulation | 11/30/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Corrections Issued | HORACE FULTZ |
| ELECTRICAL-Rough | 2/10/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/10/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/11/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 2/11/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 2/11/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 2/11/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 2/18/2022 | Approved | JUSTIN CURTIS |
| Drywall Nailing | 3/10/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 3/10/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 4/26/2022 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 4/28/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 4/28/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 4/28/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 4/28/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 4/28/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 4/28/2022 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 4/28/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 4/29/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Service/Power Release | 4/29/2022 | Approved | JOAQUIN GREENOUGH |