18550 1/2 W VALERIO ST 91335

Certificate Information: 18550 1/2 W VALERIO ST 91335

Application / Permit
21010-10000-00370
Plan Check / Job No.
B21LA01175
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: NEW DETACHED ADU IRREGULAR SHAPE 24'-5" X 30'-10" 596 SQ.FT.
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 ARSALAN SHABESTARI
Corrections Issued 2/23/2021 ARSALAN SHABESTARI
Quality Review Completed 3/5/2021 HERNAN ARREOLA
Plan Check Approved 10/1/2021 ARSALAN SHABESTARI
Issued 10/20/2021 APPLICANT
CofO in Progress 10/3/2022 JEFFREY BULL
Permit Finaled 11/19/2022 MICHAEL SMITH
CofO Issued 11/19/2022 MICHAEL SMITH
Permit Finaled 11/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/5/2021 GUILLERMO PETRA
Construction near power lines Cleared 5/13/2021 RIDWAN HARDY
Construction within easement Cleared 5/13/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/18/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 5/18/2021 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 7/9/2021 GREGORY HOERNER
Low Impact Development Cleared 8/5/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 8/9/2021 GABRIEL ROBLES

Contact Information

Contractor Sargsyan Albert; Lic. No.: 965820-B 1812 W BURBANK BLVD #169      BURBANK, CA 91506
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/25/2021 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 10/29/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/22/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 12/22/2021 Approved VINCENT HANLEY
Green Building Rough 12/22/2021 Approved VINCENT HANLEY
HVAC-Rough 12/22/2021 Approved VINCENT HANLEY
PLUMBING-Rough 12/22/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/27/2021 Partial Approval VINCENT HANLEY
Insulation 1/18/2022 Conditional Approval JESUS PINEDA
Drywall Nailing 1/20/2022 Approved VINCENT HANLEY
Insulation 1/20/2022 Approved VINCENT HANLEY
Shower Pan 3/31/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 4/19/2022 Approved JUSTIN HAWLEY
Shower Pan 4/19/2022 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 5/3/2022 Partial Approval VINCENT HANLEY
Green Building Final 5/3/2022 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Not Ready VINCENT HANLEY
Sewer 5/3/2022 Approved VINCENT HANLEY
Smoke Detectors 5/3/2022 Not Ready for Inspection VINCENT HANLEY
Underground Mechanical 5/3/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 5/3/2022 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 9/16/2022 Approved JEFFREY BULL
Final 9/16/2022 Not Ready for Inspection JEFFREY BULL
Green Building Final 9/16/2022 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved JEFFREY BULL
Service/Power Release 9/16/2022 Not Required JEFFREY BULL
Smoke Detectors 9/16/2022 Approved JEFFREY BULL
Verify Sprinkler Sign Off 9/16/2022 Approved JEFFREY BULL
Final 10/3/2022 OK to Issue CofO JEFFREY BULL
Green Building Final 10/3/2022 Approved JEFFREY BULL