10611 W ASHBY AVE 90064

Certificate Information: 10611 W ASHBY AVE 90064

Application / Permit
21010-10000-00368
Plan Check / Job No.
B21LA01163
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU PER GCS 65852.2 (e)(1)(B) WITH ATTACHED GARAGE "Comply with Department Order effective date 03/17/2020."
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 11/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 MAHNAZ NOURHASHEMI
Corrections Issued 2/17/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 3/2/2021 JASON HEALEY
Building Plans Picked Up 3/4/2021 APPLICANT
Applicant returned to address corrections 4/15/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 6/8/2021 MAHNAZ NOURHASHEMI
Issued 6/8/2021 APPLICANT
CofO in Progress 10/28/2022 MICHAEL PELHAM
Permit Finaled 11/2/2022 DANIEL ORRANTE
CofO Issued 11/2/2022 DANIEL ORRANTE
Permit Finaled 11/2/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/11/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 3/15/2021 CATHERINE ADROVER
Sewer availability Cleared 3/16/2021 CATHERINE ADROVER
Construction near power lines Cleared 3/23/2021 TINA MIRANDA
Specific Plan Cleared 3/25/2021 VALERIA CEJA
Hydrant and Access approval Cleared 4/24/2021 ROBERT DUFF
Low Impact Development Cleared 5/23/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/25/2021 DINAH GARIN
GPI Written Notices Cleared 6/8/2021 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 6/8/2021 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Jung,, Jason Stanley; Lic. No.: C80569 106 N ROSEMEAD BLVD STE 204      PASADENA, CA 91107

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/8/2021 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/8/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/8/2021 Partial Approval KEVIN SARGSYAN
Grounding or Bonding 7/8/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 7/16/2021 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/16/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 7/16/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 7/16/2021 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/20/2021 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/20/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 9/20/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 9/20/2021 Partial Approval KEVIN SARGSYAN
Sewer 9/20/2021 Approved KEVIN SARGSYAN
Gas Test 10/4/2021 Approved DEANDRE HOFFMAN
PLUMBING-Rough 10/4/2021 Approved DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 10/7/2021 Approved KEVIN SARGSYAN
HVAC-Rough 10/14/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 11/17/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 11/17/2021 Corrections Issued KEVIN SARGSYAN
Verify Sprinkler Sign Off 11/17/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/24/2021 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 11/30/2021 Approved KEVIN SARGSYAN
Green Building Rough 11/30/2021 Approved KEVIN SARGSYAN
Insulation 12/6/2021 Approved KEVIN SARGSYAN
Drywall Nailing 12/16/2021 Approved DEANDRE HOFFMAN
Shower Pan 1/7/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 1/20/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 8/25/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 8/29/2022 Approved OGANES TARAKHCHYAN
Green Building Final 8/29/2022 Approved OGANES TARAKHCHYAN
Gas Test 8/31/2022 Approved OGANES TARAKHCHYAN
Service/Power Release 8/31/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 9/22/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 9/22/2022 Approved OGANES TARAKHCHYAN
Final 10/27/2022 Partial Approval OGANES TARAKHCHYAN