2008 S CHARITON ST 90034
Certificate Information: 2008 S CHARITON ST 90034
- Application / Permit
- 21010-10000-00343
- Plan Check / Job No.
- B21LA01085
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: NEW detached ADU
- Permit Issued
- Issued on 6/3/2021
- Issuing Office
- Current Status
- CofO Issued on 8/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 1/30/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/3/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/13/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 5/31/2021 | ARSALAN SHABESTARI |
| Issued | 6/3/2021 | APPLICANT |
| CofO in Progress | 7/29/2022 | EVAN COOPER |
| Permit Finaled | 8/18/2022 | DANIEL ORRANTE |
| CofO Issued | 8/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 2/17/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 3/24/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/12/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | ROSA SILVA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2021 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 9/15/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 9/15/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 9/27/2021 | Approved | EVAN COOPER |
| Sewer | 10/18/2021 | Approved | KENNETH NAGLE |
| Deputy Wood Construction | 10/26/2021 | Conditional Approval | EVAN COOPER |
| Underground Mechanical | 10/29/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 11/30/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/27/2021 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 1/14/2022 | Approved | DEANDRE HOFFMAN |
| HVAC-Rough | 2/10/2022 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 2/28/2022 | Approved | EVAN COOPER |
| Green Building Rough | 2/28/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 2/28/2022 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 2/28/2022 | Approved | EVAN COOPER |
| Insulation | 3/4/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 3/11/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/11/2022 | Approved | EVAN COOPER |
| Shower Pan | 3/11/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/14/2022 | Approved | EVAN COOPER |
| Shower Pan | 3/14/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/20/2022 | Approved | EVAN COOPER |
| Gas Test | 5/20/2022 | Approved | EVAN COOPER |
| HVAC-Final | 5/20/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 5/20/2022 | Approved | EVAN COOPER |
| Service/Power Release | 5/20/2022 | Approved | EVAN COOPER |
| Green Building Final | 6/3/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 6/3/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| HVAC-Final | 7/6/2022 | Approved | EVAN COOPER |
| Final | 7/29/2022 | OK to Issue CofO | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 7/29/2022 | Approved | EVAN COOPER |