2008 S CHARITON ST 90034

Certificate Information: 2008 S CHARITON ST 90034

Application / Permit
21010-10000-00343
Plan Check / Job No.
B21LA01085
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: NEW detached ADU
Permit Issued
Issued on 6/3/2021
Issuing Office
Current Status
CofO Issued on 8/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 ARSALAN SHABESTARI
Corrections Issued 1/30/2021 ARSALAN SHABESTARI
Quality Review Completed 2/3/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/13/2021 ARSALAN SHABESTARI
Plan Check Approved 5/31/2021 ARSALAN SHABESTARI
Issued 6/3/2021 APPLICANT
CofO in Progress 7/29/2022 EVAN COOPER
Permit Finaled 8/18/2022 DANIEL ORRANTE
CofO Issued 8/18/2022 DANIEL ORRANTE
Permit Finaled 8/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/11/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 2/17/2021 CECILIO NAVARRO
Sewer availability Cleared 2/17/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 3/24/2021 MATTHEW CRAIG
Low Impact Development Cleared 5/12/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/14/2021 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/9/2021 Approved EVAN COOPER
Footing/Foundation/Slab 9/15/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 9/15/2021 Partial Approval EVAN COOPER
Footing/Foundation/Slab 9/27/2021 Approved EVAN COOPER
Sewer 10/18/2021 Approved KENNETH NAGLE
Deputy Wood Construction 10/26/2021 Conditional Approval EVAN COOPER
Underground Mechanical 10/29/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 11/30/2021 Approved EVAN COOPER
Interior/Exterior Lathing 12/27/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 1/14/2022 Approved DEANDRE HOFFMAN
HVAC-Rough 2/10/2022 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 2/28/2022 Approved EVAN COOPER
Green Building Rough 2/28/2022 Approved EVAN COOPER
HVAC-Rough 2/28/2022 Approved EVAN COOPER
Verify Sprinkler Sign Off 2/28/2022 Approved EVAN COOPER
Insulation 3/4/2022 Corrections Issued EVAN COOPER
Drywall Nailing 3/11/2022 Approved EVAN COOPER
Interior/Exterior Lathing 3/11/2022 Approved EVAN COOPER
Shower Pan 3/11/2022 Approved EVAN COOPER
Interior/Exterior Lathing 3/14/2022 Approved EVAN COOPER
Shower Pan 3/14/2022 Approved EVAN COOPER
PLUMBING-Final 5/12/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 5/20/2022 Approved EVAN COOPER
Gas Test 5/20/2022 Approved EVAN COOPER
HVAC-Final 5/20/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 5/20/2022 Approved EVAN COOPER
Service/Power Release 5/20/2022 Approved EVAN COOPER
Green Building Final 6/3/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 6/3/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Not Ready OGANES TARAKHCHYAN
HVAC-Final 7/6/2022 Approved EVAN COOPER
Final 7/29/2022 OK to Issue CofO EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 7/29/2022 Approved EVAN COOPER