2051 W LAS COLINAS AVE 90041

Certificate Information: 2051 W LAS COLINAS AVE 90041

Application / Permit
21010-10000-00335
Plan Check / Job No.
B21LA01079
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY A.D.U. AT REAR OF LOT (800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
Permit Issued
Issued on 9/30/2021
Issuing Office
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 LAWRENCE QUIRANTE
Corrections Issued 2/7/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/12/2021 SINA KHOSRAVI
Plan Check Approved 8/16/2021 SINA KHOSRAVI
No Progress 8/16/2021 SINA KHOSRAVI
Plan Check Approved 9/30/2021 ZAW HAN
Issued 9/30/2021 APPLICANT
Building Plans Picked Up 10/1/2021 APPLICANT
CofO in Progress 4/7/2022 CRAIG VAUGHAN
CofO Issued 4/19/2022 DEROLD HAUFF
Permit Finaled 4/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/18/2021 JUAN ASHTON
Address approval Cleared 4/5/2021 JUAN ASHTON
Sewer availability Cleared 4/5/2021 JUAN ASHTON
Low Impact Development Cleared 6/10/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/11/2021 THAN WIN
Grading Pre-Inspection Cleared 8/16/2021 LAWRENCE QUIRANTE

Contact Information

Contractor Rebuilt Homes Inc; Lic. No.: 1063540-B 2201 N LAKEWOOD BLVD STE D643      LONG BEACH, CA 90815
Engineer Gonzalez,, Felix Bolivar; Lic. No.: C64738 14619 CATALINA AVE      GARDENA, CA 90247

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/4/2021 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/12/2021 Partial Approval CRAIG DAVIS
Underground Mechanical 10/14/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 11/17/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 11/17/2021 Corrections Issued CRAIG VAUGHAN
Green Building Rough 11/17/2021 Approved CRAIG VAUGHAN
HVAC-Rough 11/17/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 11/17/2021 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 11/17/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 11/22/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 11/22/2021 Approved CRAIG VAUGHAN
Shower Pan 11/22/2021 Approved CRAIG VAUGHAN
Drywall Nailing 12/7/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/7/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/24/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 2/24/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/24/2022 Approved CRAIG VAUGHAN
Green Building Final 2/24/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 2/24/2022 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 2/24/2022 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 2/24/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 3/29/2022 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 3/29/2022 Approved SCOTT FINNILA
Smoke Detectors 3/29/2022 Approved SCOTT FINNILA
ELECTRICAL-Final 3/31/2022 Approved SCOTT FINNILA
Final 3/31/2022 Corrections Issued SCOTT FINNILA
Gas Test 3/31/2022 Approved SCOTT FINNILA
Green Building Final 3/31/2022 Approved SCOTT FINNILA
HVAC-Final 3/31/2022 Approved SCOTT FINNILA
PLUMBING-Final 3/31/2022 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/31/2022 SGSOV Approved SCOTT FINNILA
Final 4/6/2022 OK to Issue CofO CRAIG VAUGHAN