1307-1309 W 38TH ST 90062

Certificate Information: 1307-1309 W 38TH ST 90062

Application / Permit
21010-10000-00327
Plan Check / Job No.
B21LA01071
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY DUPLEX
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
CofO Issued on 6/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 DANIEL YIP
Corrections Issued 2/8/2021 DANIEL YIP
Quality Review Completed 2/11/2021 ALLEN MANALANSAN
Plan Check Approved 10/7/2021 DANIEL YIP
Issued 10/7/2021 APPLICANT
Building Plans Picked Up 10/8/2021 APPLICANT
CofO in Progress 1/18/2023 SABAS ALONSO
CofO in Progress 1/25/2023 CHARLES BOGHOSKHAN
CofO in Progress 5/19/2023 SABAS ALONSO
CofO in Progress 6/7/2023 SABAS ALONSO
CofO in Progress 6/24/2023 DONALD CRICHLOW
CofO in Progress 6/26/2023 SABAS ALONSO
Permit Finaled 6/26/2023 DEROLD HAUFF
CofO Issued 6/26/2023 DEROLD HAUFF
Permit Finaled 6/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/22/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 2/22/2021 CECILIO NAVARRO
Sewer availability Cleared 2/24/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 4/25/2021 MATTHEW CRAIG
Frnt yard landscape/Water mgmt Cleared 6/17/2021 MAXFIELD VERMY
Low Impact Development Cleared 8/2/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/4/2021 CECILIO NAVARRO

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/9/2021 Approved SABAS ALONSO
Footing/Foundation/Slab 11/17/2021 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Partial Approval SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 2/9/2022 Corrections Issued SABAS ALONSO
HVAC-Rough 2/9/2022 Approved SABAS ALONSO
PLUMBING-Rough 2/9/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 2/17/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 2/17/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 2/17/2022 Conditional Approval SABAS ALONSO
PLUMBING-Rough 2/17/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 2/17/2022 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 2/24/2022 Approved SABAS ALONSO
Green Building Rough 2/24/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 2/24/2022 Approved SABAS ALONSO
Insulation 3/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 3/2/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 3/8/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 3/8/2022 Approved SABAS ALONSO
Final 7/13/2022 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 7/13/2022 Approved SABAS ALONSO
Smoke Detectors 7/13/2022 Approved SABAS ALONSO
Final 12/20/2022 Corrections Issued SABAS ALONSO
Final 1/17/2023 Not Ready for Inspection SABAS ALONSO
Final 5/18/2023 Conditional Approval SABAS ALONSO
Final 6/7/2023 Corrections Issued SABAS ALONSO
Final 6/23/2023 OK to Issue CofO SABAS ALONSO